Skip to main content

From the latest Construction Alert: how construction (at the arena site) "progresses as scheduled" but may require extra shifts, and "schedule maintenance" (at the rail yard) requires weekend work

There's no major news, as far as I can tell, in the latest two-week Atlantic Yards Construction Alert, dated 11/21/11 and distributed yesterday by Empire State Development (after preparation by developer Forest City Ratner).

But I do want to point out some curious, recurring, "Orwellian, almost" language. The heading regarding the arena site states "Construction at the Arena Site Progresses as Scheduled."

However, the section also mentions that a second shift by the steel erector/stadia installer, while not expected in the next two weeks, will be re-evaluated after this period, while some weekday overtime may be needed and work on Saturdays will continue.

In other worse, "scheduled" progress requires overtime. Similarly, fireproof painting of the structural steel will continue on a second shift.

Also, waterproofing of the interior walls of the east storm water retention tank may be performed on a second shift. The tie-ins for the piping for the storm/sanitary/water services to the arena at 6th & Pacific as well as Dean & Flatbush may require a second and/or third shift, as well as weekend work.

The vertical transportation (aka elevator) contractor is expected to work a second shift during this period.

By contrast, the heading on the section regarding railyard work is "What's Happening in the Rail Yard." It also states:
Due to the need to expedite all of this work for overall schedule maintenance, it will be progressed on Saturdays and (selected Sunday & Holidays).
In other words, "schedule maintenance," like "scheduled" progress, requires overtime.

The text below is excerpted from the latest document, with the bolded text indicating what's new compared to the previous alert.

Arena Site Foundation & Perimeter Walls
• Backfill placement along the exterior 6th Avenue elevation has been completed

• The installation of temporary weather walls (visqueen & tarps) as well as temporary rubber roofing, to provide protection through the winter months, is expected to start this reporting period.
It previously said "expected to continue."

Arena Site/Mechanical, Electrical, and Plumbing
The construction fence at the ConEd vault will be revised to allow ConEd and the Arena contractors to begin installation of primary power conduit, cable and drainage piping to the arena at this point of entry. This will require work in the street by ConEd personnel – installers and Arena contractors. Metal plates will cover the cable work in Dean Street while it is underway.

Subway entrance
Work outside the Fence

• Permits have been secured for the portions of the street immediately adjacent to the “Tip” of the project area. Concrete plank/decking in the roadway (at the corner of Flatbush and Atlantic) has been in place for some time. The southern eastbound lane of Atlantic Avenue has now been taken behind an expanded MPT in order to facilitate the removal of the planking/decking to be removed and the installation of temporary roadway restoration. This work has now commenced and is scheduled to be completed by the middle of December. A pathway for the new water main has been coordinated with the utility team and will be constructed and following the plank removal. This will then permit the next phase of the water main installation to take place which is scheduled for the beginning of the year. This expanded MPT, noted above, has been approved by DOT.
Erection of Interior Walls
Interior masonry walls in the fare array area and in the new utility rooms under the main staircase are now substantially complete. Masonry infill walls at the BMT mezzanine will follow in December and January.
Concrete
• The new roof over the new fare array area has been poured. Construction of the reinforced concrete staircase structure is substantially complete with steel treads and tiled risers to follow. Concrete foundation walls are substantially complete and construction of the station roof near the tip, at Flatbush and Atlantic Avenues, is now substantially complete. The two new escalator trusses from the fare array area to the new plaza have been set and final assembly continues. The new elevator enclosure has also been erected and elevator rail installation has commenced.
Railyard/Carlton Ave Bridge
• MPT has been in place at Carlton Ave. and Pacific Street for work on the new south abutment. Excavation to the subgrade for the south abutment foundation has been completed and the reinforced concrete footing poured. During this reporting period the contractor will start to form and install rebar for the stem wall of the new south abutment.
Railyard/East End (former Gasoline Station)
Posillico/Tully will continue working on the lagging and tieback work at this location and continue to lower the grade there. Pile-drilling in this area below grade is complete. The excavation and associated support work will be on-going for the next couple of months. Posillico/Tully will work in this area during the weekend of Nov. 25-27th to demolish and remove an existing closure wall that runs adjacent to the existing LIRR east portal. The demolition of this wall will require the use of a hoe ram to break up the concrete for removal. The work will be performed during normal working hours of 8 A.M. to 4 P.M.
Block 1129
• The Utility contractor is in the process of moving its storage areas from the southeast corner of Block 1129, lot 54 (the corner of Vanderbilt and Dean) to Block 1129, lot 21 (just east of the 752 Pacific Street building and adjacent to Pacific Street). The contractor will make every effort to move the equipment and materials to the new location during daytime work hours.
 Arena Site Work
The revised Flatbush Avenue MPT is allowing work to continue on the installation of the Flatbush Avenue fa├žade and the installation of bollards along this same stretch. Part of the overall site work for the arena block, bollard installation, commenced at the intersection of Dean and Flatbush in the area of the southern vents and will continue north along Flatbush, eventually continuing around the entire block. The bollard work is anticipated to be complete by the middle of December. Other work that will be done as part of the site work includes sidewalks, installation of pavers, street furniture, street trees, light and signal poles, way finding signage, hydrants and the canopy to the new subway entrance. Additional detail on the work will be provided as the contractor progresses.
Installation of the underground drainage is anticipated to commence within the plaza area located at the tip of the site at the end of November and continue into December.
Overtime work

This next isn't new, but repeated for reference purposes:
Please Be Advised of Anticipated Nighttime & Weekend Work
During this reporting period the following work will be performed either at night or during the weekend as noted. All work will be done pursuant to approved permits:
• Long Island Rail Road/Vanderbilt Yard/ Carlton Avenue Bridge:
o All weekdays days all locations in the yard: 6:00AM to 11:00PM
o Saturdays as required: 7:00 AM to 11:00 PM
o Sundays and Holidays as required: 8:00AM to 11:00PM
o The weekend work being performed could be in any area of the yard, and within MPT areas for which permits are on hand.
o The work hours will remain in place for a minimum of the next three months.
• Arena Site:
o Arena weekend work will be scheduled no later than close of business on the preceding Thursday, where make-up work due to weather or other delays makes it necessary. Saturday work is expected to continue for this reporting period.
o Subject to receipt of permits, a second shift shall be continued throughout this reporting  period, from 3 – 11 PM, Monday-Friday only. Also subject to receipt of permits, a third shift shall be instituted during this reporting period, from 11 PM – 7 AM, Monday –Friday only.
o Hunt has been granted a permit to allow for deliveries from 6 AM to 7 AM to the Arena site from the dispatch center. This work allows for an additional hour of deliveries to take place outside the neighborhood peak traffic patterns and reduce congestion and interference with the local traffic.
o The second shift arena contractors are noted within the arena summary above.
• NYC Transit Improvements:
o Temporary concrete road decking is substantially complete, however, in the event there is a need to do any related work, such work will be performed at night per DOT regulations.
Traffic will be restored every morning according to DOT stipulations.
As noted above, work will be performed to repair steel within the BMT Tunnel and will be conducted under a BMT GO during the weekend of November 26th as approved by the NYCT. Additionally, work related to of the BMT structure and below grade concrete, steel and MEP work may be conducted on Saturdays November 26th and December 3rd, during this reporting period.
• Arena Site Work: • Block 1129 – staging area:
o Contractors conducting night work may have cause to enter and exit this area as it serves as a staging and material/equipment storage area.
During the course of work, conditions may be encountered at the site which may warrant the need for night and/or weekend work. Work will be done pursuant to approved permits.

AY Construction Alert 11-21-2011

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…