Skip to main content

FCR to CB 8: evasive and disingenuous on project timing, jobs, bridge opening

Forest City Ratner's announcement in May that Atlantic Yards was moving ahead generated several questions from Brooklyn Community Board 8, which got back a response that is often evasive, vague, and disingenuous.

According to the letter, sent July 18, the developer is unwilling to commit to a start date for Phase 2 nor to commit to opening the arena only when reconstruction of the adjacent Sixth Avenue bridge is complete. The developer offers a highly-qualified pledge for interim open space and, in asserting project’s benefits, likely overestimates the number of permanent jobs in Phase 1 by a factor of two.

The letter, from Senior VP Scott Cantone, was sent to CB8 Chairman Robert Matthews and cc’d to various public and elected officials. CB8 has not yet publicly responded.

(I've added bolding for emphasis in several places.)

Timetable

The first question involved the timetable:
1. Besides signing an anchor tenant for the B1 building, what other dependencies must be met for the remaining buildings in Phase 1 to be built... What is the timetable for resolving these dependences?

The response:
The completion of buildings in Phase 1... is dependent on factors typical to any large-scale development, such as:
  • completing acquisition of the site
  • finalizing project documentation and agreements with the Empire State Development Corporation
  • securing financing; and
  • finalizing agreements with the City of New York for affordable housing programming.
We are progressing in all these areas, and intend to begin construction on the building on the Arena Block according to the schedule outlined in the press a few weeks ago: The Arena and the first of the residential buildings are expected to be completed simultaneously. The next Arena Block residential building is expected to go into construction 6 months later, and the final residential building is expected to begin 6 months after that.

However, it is hardly typical that the acquisition of a site depends on eminent domain, which in this case has been contested in court. Also, the towers depend on the arena, and right now there’s no financing for the arena. That’s probably why Cantone did not pledge any start date.

What about Phase 2?

As I’ve reported, there’s no start date for Phase 2, and CB8 wanted to know more:
2. The City and State funding agreement don’t specify a deadline for the construction for Phase 2, but most of the public benefits associated with the project are dependent on Phase 2. Is Forest City planning to commit to a start date for Phase 2, and agree to remedies for the community if the start date is not achieved?

The response:
FCR intends to start Phase 2 as soon as possible. However, the tremendous public benefits that come immediately with Phase 1 should not be overlooked.

Having ignored the question, Cantone switched the subject and ignored the question of remedies:
The completion of Phase 1 will bring hundreds of affordable housing units for low- and middle-income families, representing 30% of all residential units constructed on the Arena Block. The Arena itself will be a major civic facility for Brooklyn. Furthermore, Phase 1 will generate over 3000 new, permanent jobs as well as significant new tax revenues for the City and State, and it will include significant public amenities, such as the Urban Room (which includes approximately 10,000 square feet of publicly accessible space) and the new entryway into the subway.

However, the Urban Room and subway issue would serve the arena and the buildings as much as any surrounding community, including that in CB 8. The Arena would not be “for Brooklyn” if it’s rented for $100,000, even if the developer, as per the Community Benefits Agreement, makes it available ten times a year for community groups. (FCR has since said the rental price would be lower.)

And the benefits would hardly come immediately if the developer has a 12+ years to build Phase 1 and there's no anchor tenant for Building 1.

3000 new permanent jobs?

Cantone’s pledge of 3000 new jobs is doubtful, so let’s do some math.

Building 1, with 650,000 square feet of office space, at 250 sf per job (the measure used by the city and state), could accommodate 2600 jobs. However, the New York City Economic Development Corporation (NYCEDC), in an analysis of an earlier configuration, calculated a 7 percent vacancy rate (182), which would mean 2418 jobs. NYCEDC also suggested that only 30 percent of the jobs would be new to New York, rather than moved from Manhattan. That would mean only 725 new office jobs at Atlantic Yards.

According to a memo from the Empire State Development Corporation, there would be 453 arena jobs; however, as the New York Observer reported in 2005, the arena jobs (400 in that article) would be subject to union rules and may be filled with current employees. Let’s estimate 60% new jobs from 453: 272.

According to the ESDC memo, there would be one building services job for every 20 units; at 1500 units (which represents 1.5 million square feet, the minimum over 12 years in City Funding Agreement), that means 75 building services jobs. At 2000 units, that would be 100 jobs.

Parking is 92 jobs at full buildout of 3670 spaces; but there would only be 2346 spaces in Phase 1; that same ratio, 63.9%, yields 59 jobs.

There would be 91,000 gsf of retail space in Phase 1; at 300 gsf per job, according to the ESDC memo, that means 303 jobs.

So my calculation for the total number of jobs for Phase 1 would be 1434 (725 + 272 + 75 + 59 + 303). There could be a few more building service jobs, potentially more new office jobs, and also some spinoff jobs, but for now, Cantone should be asked for details rather than taken on faith.

Worker numbers?

CB 8 asked:
3. Demolition of buildings in the Phase 2 site was claimed to have been necessary to create construction staging and worker parking areas during Phase 1. Now that only the arena and one building are going to be built in the first stage of Phase 1, how has your estimate of the peak number of workers at the site changed? What percentage of those workers are you now projecting will drive to the site?

(Note that CB8 only includes in its boundaries Phase 2.)

The response:
As mentioned above, the scope of Phase 1 has not changed from what was approved as part of ESDC’s General Project Plan. However, the schedule has been delayed approximately two years as a result of litigation. The number of construction workers on the site will remain generally the same as was disclosed in the Final Environmental Impact Statement (FEIS) for both Phase 1 and Phase 2.

Well, the scope may not have been changed, but the developer has said nothing about Site 5, the site now occupied by Modell’s and P.C. Richard. So “generally the same” may contain some leeway.

Staging needs

CB 8 asked:
4. Since the construction of B1 and the cluster buildings in Phase 1 will be delayed, how has your assessment of the amount of space required for staging changed? Are you considering the use of the areas of the Phase 1 site adjoining the arena and the first residential building for staging and worker parking instead of using some or all of the Phase 2 site? If the unbuilt areas of Phase 1 won’t be used for staging, how will the space be used?

Cantone replied:
The staging areas identified in the FEIS remain the same. The construction of both the Arena and the LIRRR railyard, which will be undertaken as part of Phase 1, requires the use of Block 1129 for staging. At the time the Arena opens, we anticipate a portion of the Phase 2 site will continue to be used for development, construction staging or other project uses to support the development of the platform over the LIRR new yard, the construction of the residential buildings, and the open space that is part of Phase 2.

He didn't mention that a significant portion of the Phase 2 site would be used for interim surface parking.

Buildings as buffer

CB 8 asked:
5. The Atlantic Yards FEIS refers to the buildings around the arena as a buffer for locating the arena in a residential neighborhood. With only one residential building slated to be complete at the time of the arena opening, that buffer will not be in place at that time. In addition, due to the changes in the construction timetable, the impact of the arena on the residential and commercial areas around the project, (including the arena’s radical swings from dormancy to intense activity), will no longer be compensated for by the residential high density of the ring buildings. The one residential building proposed to be complete at the time of the arena opening is roughly the same number of residential units as the number of units displaced b the project as a whole. Please detail how you plan to prevent the arena from affecting the residential and commercial areas around the project adversely during the extended buildout of the project.

Cantone responded:
In the event that any of the development sites that surround the Arena (Buildings 1-4) are not in construction by the time that the Arena open, FCRC will create temporary public open spaces between the Arena and the surrounding streets; however, we anticipate that construction of Phase 1 will be complete or underway at the time of the Arena opening.

The pledge for temporary open space seems iffy, given the broad scope of “in construction.” Even if there were temporary open space, it wouldn’t arrive until the arena opens, at least three years down the line.

Displacement issues

Cantone also took issue with the claim that the building would contain roughly the same number of residential units as the number displace:
This is factually incorrect. The proposed residential building will offer approximately 300 residential units.

He’s correct. Chapter 4 of the FEIS, Socioeconomic, states
The proposed project would directly displace 171 residential units housing an estimated 410 residents.

It also states:
[I]t was estimated that the study area contains approximately 2,929 households that are potentially at risk of indirect residential displacement.

However, the study doubts that the total is at risk from the project, citing ongoing gentrification, because new housing units could relieve market pressure, and because most of the at-risk households would be more than a half-mile away. I wrote in July 2006 that one of the reasons--that the housing would be similar--was bogus.

New open space?

CB 8 asked:
6. What is the open space plan for Phase 1 across the new timetable you have recently released. Will there be any open space added to the project in Phase 1 to compensate for the loss of the arena roof as open space?

Cantone repeated the answers about the Urban Room and temporary open space, adding:
As noted above, in the event that a development site on the Arena Block is not in construction or needed for other project purposes by the time the Arena is completed, FCRC will create temporary open spaces that will persist until such site is needed for development or construction activities.

Actually, Cantone first said that open space would be created if a development site is “in construction” but here he's added a broad qualifier: “needed for other project purposes.” That gives the developer a lot of leeway.

Bridges open?


Question 7 confirmed plans for indoor parking. The final question from CB 8 concerned bridges:
8. Will the Carlton Avenue and 6th Avenue bridges be complete and open when the arena is opened?

Cantone responded:
Both the Carlton Avenue and the 6th Avenue bridges are anticipated to be open when the Arena opens.

An ESDC spokesman told me last November, “Forest City Ratner tells us that while the arena might be able to open without the bridge in operation, the goal is to have the bridge open in coordination with the arena's opening."

Note that “anticipated” is a weasel word. The Carlton Avenue bridge is undergoing reconstruction and surely would be finished before the Sixth Avenue bridge is addressed. At the current timetable, the Sixth Avenue bridge should be open by early 2011, providing a good chunk of time before the basketball season begins in October--but there can always be snags.

Who's in charge?

Local public officials and community boards surely would not want the Sixth Ave bridge closed during an arena event, since the traffic problems could be ruinous. But Forest City Ratner certainly wouldn't want to miss an arena opening at the beginning of the basketball season: there are suites to sell and a naming rights contract to fulfill.

In that case, there might be significant tension between the interests of the developer and the interests of the public.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…