Forest City: B2 modular tower requires another extension on forbearance agreement with mortgage lender; result not assured

Maybe I'm reading too much into the tea leaves, but language in two successive filings with the Securities and Exchange Commission suggests that Forest City Enterprises is somewhat less confident that its mortgage loan regarding the ill-fated modular tower, B2 (aka 461 Dean Street) will be extended.

Or maybe things are just moving slowly.

May 2015 statement

Consider the language in the 5/4/15 Form 10-Q:
At March 31, 2015, we have $50,093,000 capitalized on the Consolidated Balance Sheet related to B2 BKLYN. Based on the most current information available, total project costs are estimated to be $162,100,000, after giving effect to an impairment charge recorded in 2014. Significant estimates and assumptions were used to develop the estimated total project costs and may change in the future.
Subsequent to the construction stoppage in 2014, we received a notice of default on the nonrecourse mortgage secured by B2 BKLYN. We have since entered into a forbearance agreement with our lender which expires on June 8, 2015 and are currently in negotiations for a longer term agreement. In the event we are unable to complete the negotiation of a longer term agreement, or cure the default, we may be required to repay the current outstanding balance of $45,000,000 currently secured by, amongst other things, $37,500,000 of restricted bond proceeds included in restricted cash, $10,000,000 of cash in escrow and an equity letter of credit of $9,300,000. In addition, we may be required to continue funding the completion of B2 BKLYN with equity until the uncertainties regarding its construction are resolved.
(Emphases added)

August 2015 statement

The 8/4/15 Form 10-Q similarly notes the legal dispute with former partner Skanska USA and Forest City's decision to buy out Skanska’s 50% ownership interest in the modular factory in the Brooklyn Navy Yard and to re-start work at the factory and resume vertical construction. Construction completion is estimated to be finished in the third quarter of 2016. (That doesn't mean it will have a Certificate of Occupancy by then, however.)

The document continues:
At June 30, 2015, we have $74,182,000 capitalized on the Consolidated Balance Sheet related to B2 BKLYN. Based on the most current information available, total project costs are estimated to be $162,100,000, after giving effect to an impairment charge recorded in 2014. Significant estimates and assumptions were used to develop the estimated total project costs and may change in the future.
Subsequent to the construction stoppage in 2014, we received a notice of default on the nonrecourse mortgage secured by B2 BKLYN. We have since entered into a forbearance agreement with our lender which expires on September 8, 2015, and we may seek another extension; however, we can provide no assurance that our lender will agree to extend the forbearance agreement. Depending on the outcome of our lender discussions, we may be required to repay the current outstanding balance of $45,000,000 currently secured by, amongst other things, $37,500,000 of restricted bond proceeds included in restricted cash, $10,000,000 of cash in escrow and an equity letter of credit of $9,300,000. In the meantime, we continue to fund construction costs with equity.
The statement "lender discussions" implies that they are already seeking another extension, but "we may seek" suggests they haven't started. They have little more than a month.

The Form 10-Q also discloses "Risks Relating to Our Business":
In the “We Are Exposed to Additional Development Risk in Connection with Using a New Construction Methodology on B2 BKLYN Modular Construction, Litigation Risks, and Owning a Factory to Produce the Modular Units” risk factor in the 2014 Annual Report, we disclosed risks associated with the construction of B2 BKLYN, an apartment building under construction in Brooklyn, New York. The following updates and supplements that information as of June 30, 2015.
During the six months ended June 30, 2015, we restarted work at the factory used to construct the modular units used in the B2 BKLYN project, including fabrication and assembly of modular units, and we resumed vertical construction during the three months ended June 30, 2015. Based on the latest information available, we estimate the construction will be completed in the third quarter of 2016. Although work has been resumed at the factory, the project may continue to encounter delays, and we may fail to satisfy completion deadlines set forth under the lending arrangements for the project and the lenders may not be willing to extend such deadlines. Failure to meet the completion deadlines could result in a default under such lending arrangements with a resulting acceleration of the debt and foreclosure of the project, as well as reputational damage.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…