Skip to main content

Public hearing set for July 29 & 30; arena due 2012, 25 years to get Phase 2 started

A Empire State Development Corporation (ESDC) legal notice (below; click to enlarge), which takes some three-quarters of a page in today's New York Post announces a public hearing on the Atlantic Yards Modified General Project Plan to be held from 2-5 pm and 6-8 pm on July 29 and July 30.

The location: the Klitgord Auditorium (285 Jay Street) of New York City Technical College, where the epic 8/23/06 hearing on Draft Environmental Impact Statement and General Project Plan was held.

Speakers will be limited to three minutes. (Let's see if that's strictly enforced.) Comments will be accepted for 30 days after the close of the hearing. That suggests that the ESDC board will vote to approve the plan in early September.

The schedule is related to developer Forest City Ratner's need to tax-exempt bond financing for the arena by the end of the year. The financing would last approximately 33 years.

Time limits: 6 years, 12 years, 25 years

The hearing notice, for the first time, imposes a 25-year deadline on the project as a whole, though I read that as 25 years to get construction started, not completed. So AY indeed would take "decades," as ESDC CEO Marisa Lago has predicted.

It states that the developer "shall use commercially reasonable efforts to construct the Arena by 2012." (I've written previously that Forest City Ratner's announced 2011 opening date is dubious.) However, as stated in the State Funding Agreement, the developer has six years without penalty to complete the arena after vacant possession of the arena block.

The State Funding Agreement says the developer has 12 years without penalty to complete the buildings on the arena block after vacant possession. The legal notice states that the interim leases for the arena block will expire no later than the 12th anniversary of vacant possession. I read that as saying that construction must have begun, but not necessarily completed.

(Interim leases permit demolition, infrastructure construction, and foundation construction, but not above-ground improvements without the consent of the ESDC.)

Similarly, the legal notice states that the interim leases for the rest of the project site east of Sixth Avenue will expire no later than the 25th anniversary of vacant possession of the arena block or any other properties taken by eminent domain in the first stage. Again, I read that as requiring construction to begin, not necessarily completed.

The deadlines are subject to extension for force majeure.

Comments

  1. For good reasons, the EDPL clearly provides that a project be completed in 10 years. Under that state law, which controls what occurs with Atlantic Yards, there is no provision for a 25 year project. Such a timeframe, from the outset, is unlawful, pure and simple.

    ReplyDelete
  2. Let me amend my comment to state that a project proceeding under eminent domain must be materially improved within 10 years. This 10 year limitation is intended to forestall condemnation blight.

    While materially improved is different than completed, it contemplates a project far more advanced than vacant land. Under this standard, construction must be well under way.

    Furthermore, a 16-tower project would have to show much more progress than an 1-tower project.

    ESDC's Atlantic Yards Project documentation allows for most of the towers to be built on a timeframe that is 2 1/2 times what the law contemplates. That is unlawful.

    ReplyDelete

Post a Comment

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…