Forest City: B2 modular tower requires another extension on forbearance agreement with mortgage lender; result not assured

Maybe I'm reading too much into the tea leaves, but language in two successive filings with the Securities and Exchange Commission suggests that Forest City Enterprises is somewhat less confident that its mortgage loan regarding the ill-fated modular tower, B2 (aka 461 Dean Street) will be extended.

Or maybe things are just moving slowly.

May 2015 statement

Consider the language in the 5/4/15 Form 10-Q:
At March 31, 2015, we have $50,093,000 capitalized on the Consolidated Balance Sheet related to B2 BKLYN. Based on the most current information available, total project costs are estimated to be $162,100,000, after giving effect to an impairment charge recorded in 2014. Significant estimates and assumptions were used to develop the estimated total project costs and may change in the future.
Subsequent to the construction stoppage in 2014, we received a notice of default on the nonrecourse mortgage secured by B2 BKLYN. We have since entered into a forbearance agreement with our lender which expires on June 8, 2015 and are currently in negotiations for a longer term agreement. In the event we are unable to complete the negotiation of a longer term agreement, or cure the default, we may be required to repay the current outstanding balance of $45,000,000 currently secured by, amongst other things, $37,500,000 of restricted bond proceeds included in restricted cash, $10,000,000 of cash in escrow and an equity letter of credit of $9,300,000. In addition, we may be required to continue funding the completion of B2 BKLYN with equity until the uncertainties regarding its construction are resolved.
(Emphases added)

August 2015 statement

The 8/4/15 Form 10-Q similarly notes the legal dispute with former partner Skanska USA and Forest City's decision to buy out Skanska’s 50% ownership interest in the modular factory in the Brooklyn Navy Yard and to re-start work at the factory and resume vertical construction. Construction completion is estimated to be finished in the third quarter of 2016. (That doesn't mean it will have a Certificate of Occupancy by then, however.)

The document continues:
At June 30, 2015, we have $74,182,000 capitalized on the Consolidated Balance Sheet related to B2 BKLYN. Based on the most current information available, total project costs are estimated to be $162,100,000, after giving effect to an impairment charge recorded in 2014. Significant estimates and assumptions were used to develop the estimated total project costs and may change in the future.
Subsequent to the construction stoppage in 2014, we received a notice of default on the nonrecourse mortgage secured by B2 BKLYN. We have since entered into a forbearance agreement with our lender which expires on September 8, 2015, and we may seek another extension; however, we can provide no assurance that our lender will agree to extend the forbearance agreement. Depending on the outcome of our lender discussions, we may be required to repay the current outstanding balance of $45,000,000 currently secured by, amongst other things, $37,500,000 of restricted bond proceeds included in restricted cash, $10,000,000 of cash in escrow and an equity letter of credit of $9,300,000. In the meantime, we continue to fund construction costs with equity.
The statement "lender discussions" implies that they are already seeking another extension, but "we may seek" suggests they haven't started. They have little more than a month.

The Form 10-Q also discloses "Risks Relating to Our Business":
In the “We Are Exposed to Additional Development Risk in Connection with Using a New Construction Methodology on B2 BKLYN Modular Construction, Litigation Risks, and Owning a Factory to Produce the Modular Units” risk factor in the 2014 Annual Report, we disclosed risks associated with the construction of B2 BKLYN, an apartment building under construction in Brooklyn, New York. The following updates and supplements that information as of June 30, 2015.
During the six months ended June 30, 2015, we restarted work at the factory used to construct the modular units used in the B2 BKLYN project, including fabrication and assembly of modular units, and we resumed vertical construction during the three months ended June 30, 2015. Based on the latest information available, we estimate the construction will be completed in the third quarter of 2016. Although work has been resumed at the factory, the project may continue to encounter delays, and we may fail to satisfy completion deadlines set forth under the lending arrangements for the project and the lenders may not be willing to extend such deadlines. Failure to meet the completion deadlines could result in a default under such lending arrangements with a resulting acceleration of the debt and foreclosure of the project, as well as reputational damage.

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.