Skip to main content

Featured Post

Atlantic Yards/Pacific Park FAQ, timeline, and infographics (pinned post)

Better late than never: work that began yesterday at northeast corner of arena block finally announced


After failing to alert people yesterday of additional work at the Atlantic Yards site--the removal of below-grade trailers at the northeast corner of the arena block--Empire State Development late this afternoon issued an after-the-fact Supplemental Report to the two-week Construction Update:
  • Arena Subcontractor trailers currently located on the B4 footprint will be removed this week. 
  • A crane will be stationed on the B4 footprint and lifting trailers up to trucks staged on street level on 6th Ave Bridge. 
  • The truck at street level will be parked pursuant to a lane closure permit, between 9 am and 3 pm, daily. 
  • Depending upon weather, trailers will be removed each day, with expected completion by the end of this week.

Comments