Besides major lawsuits, other expected litigation could delay arena construction

Besides pending major lawsuits over eminent domain and the Atlantic Yards environmental review, which may be resolved this year, other expected litigation may delay the start of arena construction, perhaps into 2010 or 2011. That means the best-case arena opening date could be 2012 (as I’ve already argued), or 2013, rather than the announced 2011.

That estimate comes from attorney George Locker, who represents tenants in two Atlantic Yards arena block footprint buildings. Without an assessment by the Empire State Development Corporation (ESDC) or independent authorities, I can’t be sure if the timetable estimate is solid, but it should certainly be part of the conversation.

Appeal coming

In September, a “smaller” lawsuit by Locker’s clients was dismissed by State Supreme Court Justice Jane Solomon, who rejected charges that the ESDC was violating a provision of state law that requires disposition of properties within a decade and that the ESDC should hold another hearing because the Atlantic Yards project has changed considerably.

Locker said an appeal must be perfected by July; he predicted oral argument in the mid-fall of 2009.

To gain control over the buildings, the ESDC would pursue “friendly condemnations;” Forest City owns the buildings but state law typically requires demolition of buildings with rent-stabilized leases to be approved by the New York State Division of Housing and Community Renewal (DHCR).

Should ESDC condemn the buildings after the pending eminent domain case is resolved but before his appeal can be heard, Locker said he will request a stay, arguing that the issues raised in his client's case should be heard first.

Back to the original argument

Should the ESDC get the go-ahead to pursue condemnation, Locker said he will also move to dismiss the effort on the grounds that the court's lack of jurisdiction, arguing that the FCR-owned properties "cannot lawfully be emptied by an end-run around the demolition procedures" of the DHCR.

ESDC attorneys have argued that state eminent domain law trumps the DHCR, and a judge has been sympathetic to that argument, though Locker's previous case raising the issue was dismissed on other grounds.

Given that Locker contends that a decision by the state’s highest court, the Court of Appeals, backed up his argument, “I believe that the Court of Appeals would want the last word,” he said.

If so, he estimated, the case could take four months in the vesting court (Supreme Court, in Brooklyn), eight months in the Appellate Division, and three to 12 months in the Court of Appeals.

Delays til 2011?

There are several variables at work, but if Locker’s right, it could take until 2011, to begin arena construction. And that's assuming no other issues hamper the project, such as the credit crunch.

Forest City Ratner has already announced plans to begin arena construction this year. As Locker's litigation go forward, look for the ESDC to try to resolve it in expedited fashion.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…