Hudson Yards project got three months for review

Here's another example in which the enviornmental review process for a large project in New York got more time than the Atlantic Yards project, and avoided a late summer hearing. As with the Yankees project mentioned yesterday, the Hudson Yards project proceeded under the auspices of New York City, rather than the Empire State Development Corporation.

Here's part of the timeline:
June 21, 2004: Draft Generic Environmental Impact Statement (DGEIS)
September 23, 2004: Public Hearing on the DGEIS held by the City Planning Commission and the Metropolitan Transportation Authority in conjunction with the ULURP process
Ten days later: Close of public comment period

That's more than three months, as opposed to 66 days for the Atlantic Yards project.