According to the latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning April 24 and circulated yesterday at 2:19 pm (a bit late) by Empire State Development after preparation by Greenland Forest City Partners (GFCP), the most notable work will occur around the arena block.
At B3 (aka 38 Sixth), the removal of hoist run (exterior elevator) will begin, as will the installation of panels where the hoist run was. Also, removal of overhead protection may occur in certain locations.
At B2 (aka 461 Dean), exterior site work to complete the sidewalk was to begin yesterday, with some work taking place overnight, as discussed in a previously distributed community notice.
Outside B11 (aka 550 Vanderbilt), part of Dean Street will be repaved where the fence was removed.
Saturday and after-hours work
As in previous weeks, Saturday work could occur at B3, B11 (550 Vanderbilt), B12 (615 Dean), and B14. Then again, pretty much nothing has been happening at B12. No weekend work is predicted at B2.
In the railyard, weekday foundation pile installation in the area of the B5 site--east of Sixth Avenue, between Pacific Street and Atlantic Avenue--may extend work hours up to 5:30 pm and may occur on Saturdays.
Also, ongoing testing for the new LIRR substation may extend weekday work hours up to 7 pm and may require work on Saturday and Sunday.
The demolition that hasn't happened
As stated in the past 23 construction updates, demolition at Block 1120, the railyard block between Sixth and Carlton avenues, could commence upon receipt of Department of Buildings and Department of Transportation permits. A community notice will be distributed. Maybe it's not actually going to happen.
At B3 (aka 38 Sixth), the removal of hoist run (exterior elevator) will begin, as will the installation of panels where the hoist run was. Also, removal of overhead protection may occur in certain locations.
Outside B11 (aka 550 Vanderbilt), part of Dean Street will be repaved where the fence was removed.
Saturday and after-hours work
As in previous weeks, Saturday work could occur at B3, B11 (550 Vanderbilt), B12 (615 Dean), and B14. Then again, pretty much nothing has been happening at B12. No weekend work is predicted at B2.
In the railyard, weekday foundation pile installation in the area of the B5 site--east of Sixth Avenue, between Pacific Street and Atlantic Avenue--may extend work hours up to 5:30 pm and may occur on Saturdays.
Also, ongoing testing for the new LIRR substation may extend weekday work hours up to 7 pm and may require work on Saturday and Sunday.
The demolition that hasn't happened
As stated in the past 23 construction updates, demolition at Block 1120, the railyard block between Sixth and Carlton avenues, could commence upon receipt of Department of Buildings and Department of Transportation permits. A community notice will be distributed. Maybe it's not actually going to happen.