Skip to main content

How ESDC practices ensure that, in cases like Atlantic Yards, the developer's choice of consultants, AKRF, will work for the state

Well, thanks to the oversight hearing last week, we finally have a public answer to a question I posed in July 2007, when I queried the Empire State Development Corporation (ESDC) about guidelines regarding hiring consultants who formerly worked on the projects that they will review.

There are virtually no guidelines. Though there's a paper-thin conflict-of-interest policy, described below, the ESDC's policy encourages the practice, essentially ensuring it will continue, absent legislative action.

If the consultant, namely AKRF, has already been hired by the project applicant--such as Columbia University or Atlantic Yards developer Forest City Ratner--that gives them an advantage, because the knowledge gained gives AKRF a head start and thus provides a more cost-effective product in the ESDC's eyes.

While state Senator Bill Perkins considers the ESDC's policy of hiring AKRF--while it was simultaneously employed by Columbia and after it had done work for FCR--a "glaring conflict," ESDC representatives defended it at the oversight hearing Perkins called January 5.

But their defense was weak, because they claimed AKRF merely provides a factual report, leaving the lay people on the ESDC board--who've been shown to be uninformed--to determine blight.

Moreover, the difference between the Columbia and AY cases--simultaneous vs. consecutive representation--is narrow, given that the project applicant pays the consultant's bills to the ESDC in either case and, as suggested by Noticing New York blogger Michael D.D. White, there's "an implicit warranty that travels with the work."

ESDC rep: AKRF situation with Columbia similar to AY

"Every project retains its own consultants," declared ESDC General Counsel Anita Laremont during the hearing, spurred by the Appellate Court decision blocking eminent domain for the Columbia University expansion.

"Do you have consultants in Atlantic Yards that were used by you that were also used by the developer," asked Perkins, who noted that two courts had criticized simultaneous representation in the Columbia case. "Like AKRF was used by you and also used by Columbia. Do you have a similar scenario with respect to Atlantic Yards?"

Laremont: "Yes."

Perkins: "Who are those, could you say?"

Laremont: "AKRF was one, for sure."

Perkins: "AKRF was used by both?"

Laremont: "Yes."



A good idea?

"From a public perception, forget the judges for the moment," Perkins followed up. "Do you think it's a good idea for the developer... and the Empire State Development to be using the same consultants for blight-type decisions, which are so controversial and which there's so much at stake? Why couldn't we find someone else other than that consultant? Why did we have to use that consultant?"

"I don't think there's a problem with it, because the analysis is really, ultimately, ours to make," Laremont responded. "So it's factual data that is being compiled, so I don't view it in the way that you do."

Of course the factual data is being compiled not in the interest of a study of neighborhood conditions but in a study aimed to find blight (and, in the case of AY, ignore data that might argue against blight).

Hiring process

"How do you go about procuring your consultants for the blight study?" Perkins asked.

"Well, we go about it in a number of different ways," Laremont said.

"In the case of this particular controversial one [Columbia], what did you do?" Perkins asked.

"We hired them based on the fact that they were already engaged in working on the Environmental Impact Statement," Laremont said, acknowledging AKRF's head start. "Because of the fact that it was our staff's view that their knowledge of the project area would vastly exceed any other firms and would be more cost-effective and would result in a quicker product being delivered."

(In the video, Executive Director Peter Davidson is at left and Executive VP Darren Bloch is at right.)

Perkins: "What was the--was there a bidding process?"

Laremont: "No, this was--"

Perkins: "Was it a no-bid contract?"

Laremont: "It was sole-source procurement, right."

The way it works

As I wrote 7/17/07, it is apparently OK for:

1) a developer (in this case Forest City Ratner) to hire consultants (in this case AKRF and Philip Habib and Associates) to advise on a development plan

2) those consultants to later evaluate the environmental impact of that development plan on the ESDC

3) that agency to pursue the potentially conflicting goals of fostering economic development and evaluating the environmental impact of such development, and

4) the consultants' work for that agency to be reimbursed by the developer.

(Above right, the cover of the Final Environmental Impact Statement for Atlantic Yards. Click to enlarge.)

Questionable process

"The noncompetitive, nonadvertised aspect is questionable, as is who’s managing the consultant," observed Hope Cohen, then of the Manhattan Institute, who's critiqued the EIS process, when in August 2008 I asked her to comment. "This question of who’s in charge is a fundamental problem in the public sector."

"Rather than [the ESDC saying] Here’s my list of approved consultants," Cohen added, "You have an applicant saying, I hired a consultant, he’s done 10% of the work so far, so please approve a noncompetitive contract to complete the work under your aegis.

She's now Associate Director of the Regional Plan Association's Center for Urban Innovation.

Another solution would be an explicit effort to ensure competition. Lobbyist Richard Lipsky, a critic of AKRF on projects other than AY (for which he works for the developer on other issues) wrote earlier this month:
[T]he eminent domain process [should] be made more equitable by creating an independent consulting mechanism so that favored consultants aren't always designated to do the state's or a developer's bidding.

In fact, we would argue that the state should be required to pay for an independent review of environmental and blight matters-and award the money to threatened property owners so that they can choose the consultants. This would create a situation where there would be at least two separate opinions that the courts might consider if a project was challenged. The current bag job scenario is no longer tenable-and the AKRF monopoly must be broken up in the interests of both fairness and good public policy.
Small circle

AKRF, hired by the developer to analyze the economic and fiscal benefits of the project, said in its 9/26/03 letter (right), "We remain excited about the project and what it can mean to Brooklyn, New York City, and the New York State."

The letter appears on p. 71 (marked 549) of this PDF a 9/29/03 Forest City Ratner presentation (3.2 MB PDF) to the ESDC, unearthed via Assemblyman Jim Brennan's lawsuit about AY financial data, which surfaced in July 2007. It also appears on p. 75 of a 10/22/03 presentation.

A map from Philip Habib and Associates appears in a 6/17/03 Forest City Ratner presentation (2 MB PDF) to the ESDC. Habib was working for Forest City Ratner when the developer in 2005 made its bid (right) to the Metropolitan Transportation Authority for the Vanderbilt Yard. (See p. 95 of this PDF).

It's unclear when the consultants stopped working for Forest City and started working for the state--I asked ESDC for information and did not receive a response--but the developer eventually hired transportation consultand San Schwartz to advise on the project, thus replacing Habib.

Schwartz, who said at a 12/5/05 Brooklyn Borough Board Atlantic Yards Committee meeting that he had been contacted by Forest City, likely began in early 2006.

Conflict-of-interest policy

A week after I raised the questions in July 2007, the ESDC told the Brooklyn Daily Eagle that AKRF's work was disclosed to the ESDC board, and after it started working for the ESDC, AKRF stopped working for FCR. So disclosure is apparently deemed sufficient.

A year later, I got the AKRF/ESDC contract via a Freedom of Information Law request. As I wrote in August 2008, it does contain a conflict-of-interest provision that prevents the consultant (AKRF) from acquiring "any interest" in the project or associated real estate. It prevents any ESDC official from sharing in any benefits from the AKRF contract. It extends the provisions to subcontractors.

However, it says nothing about serving two masters consecutively on the same project.

(Cohen said she had no good solution to the problem but suggested, at the very least, that there should be more transparency in the process, including an explanation of the exception regarding advertising the contract and competitive bidding.)

Contract cost escalates

It's also good for AKRF's bottom line to get in the door. Its initial contract with ESDC was supposed to not exceed $1.5 million. Over time, that sum more than tripled.

Lawyer's work OK'd

The issue of serving two masters was raised in another Atlantic Yards controversy.

In 2006, a coalition of Atlantic Yards opponents sued to block the ESDC's decision to allow "emergency" demolitions of five properties in the Atlantic Yards footprint. State Supreme Court Justice Carol Edmead denied the motion, but did disqualify David Paget, an environmental attorney working for ESDC who had formerly advised Forest City Ratner. (Case files here.)

A state appellate court overturned Edmead's ruling on Paget in a 2/15/06 decision, noting that Edmead erred in describing simultaneous rather than consecutive representation; that meant there was no prima facie showing of a conflict and no apparent likelihood that counsel's exercise of independent professional judgment on behalf of ESDC would be adversely affected or that counsel would be involved in representing differing interests.

The court also noted evidence that "ESDC and/or the developer had duly waived their rights as to potential conflicts of interest" and that the "appearance of impropriety" was not sufficient to warrant disqualification because it did not violate another ethical or disciplinary rule, among other reasons.

Inevitable tension

Is waiving the right to a potential conflict of interest sufficient? Consider what consultant Sam Schwartz also told the Brooklyn Borough Board Atlantic Yards Committee, according to the meeting notes:
From a consultant’s perspective, you must satisfy your client, but you must maintain your objectivity.

Those two tasks are in inevitable tension.

In court 2/14/06, as I reported, lawyers for the ESDC and Forest City Ratner said the process was not adversarial, but collaborative, since both the developer and agency are interested in having the project move forward. Jeffrey Baker, an attorney for petitioner Develop Don't Destroy Brooklyn, instead characterized it as "an arm's length transaction."

Justice Edmead agreed. She wrote in her decision:
Potentially, the interests of Ratner Companies, as an applicant or project sponsor, are adverse to the interests of the ESDC, which is charged with the responsibility to protect the environment and regulate the activities of individuals and corporations so that 'due consideration is given to preventing environmental damage.' The oft bottom-line, profit-making pursuits of real estate development corporations may not necessarily align with the stated, valid environmental interests of the ESDC.

Though the appellate court disagreed with numerous aspects of Edmead's decision, the judges did not address whether the interests of the developer and the ESDC are potentially adversarial or not.

It may look like the ESDC and Forest City Ratner are working in concert. But the ESDC, ultimately, is supposed to answer to the public. The developer answers to its shareholders.

Comments

  1. Comment Part I

    The waiver of the conflict of interest with respect to the retention of environmental attorney David Paget to work for both Forest City Ratner AND ESDC is a de facto admission that the interests of the developer and ESDC were congruent. Putting that in words Norman Oder previously used to report on this in the TimesRatnerReport (precursor to Atlantic Yards Report):

    “Lawyers for ESDC and Forest City Ratner said the process was not adversarial, but collaborative, since both the developer and agency are interested in having the project move forward.”

    (See: Tuesday, February 14, 2006, Judge won't block demolitions, disqualifies ESDC lawyer who worked for Ratner.)

    http://timesratnerreport.blogspot.com/2006/02/judge-wont-block-demolitions.html

    “. . . NOT adversarial. . . collaborative. . .both the developer and agency are interested in having the project move forward.” It’s quite similar to the unfolding of events where AKRF, hired by Ratner was then hired by ESDC not to find WHETHER there was blight, but, as their contract specified, to find and document “blight” for the record “in support of the project.”

    That then makes it very important WHAT Mr. Paget was working on. Interestingly, AKRF was (hired by both FCR and ESDC) was hired to work on two interrelated things, 1.) finding documenting support for a blight finding, and 2.) preparing an environmental impact statement (EIS) and Paget was hired to work on the latter of these two things. As Judge Edmead wrote Paget was hired to work on the latter: “ESDC essentially hired [Paget] the sponsor's current lawyer, at the sponsor's expense, to assess the environmental ramifications of the sponsor's project,"

    The blight finding and the EIS are very closely interrelated (either one could undermine the other) and both relate directly to the ability of the project to “move forward.” From the developer’s standpoint what the developer wants respecting the EIS is, as attorney Jeff Baker is quoted as saying, "to massage the process to get an outcome that favors the developer." To say that ESDC’s interest is `congruent’ is to say that ESDC has likewise decided that it wants to so massage the process, which is to say that ESDC did not want to perform what Justice Edmead correctly identified as its proper responsibility which is “to protect the environment and regulate the activities of individuals and corporations so that 'due consideration is given to preventing environmental damage.'”

    Michael D. D. White
    Noticing New York
    http://noticingnewyork.blogspot.com/

    ReplyDelete
  2. Comment Part II

    The problematic effect of the Paget’s conflict was very evident in other ways. What probably ought to be considered a serious deficiency in the EIS, that it did not include an evaluation of the alternative plan of rival developer Extell, was allegedly explained by Mr. Paget himself by attributing the deficiency to his conflict of interest. According to attorney Baker, when people at a meeting of the Borough Board Atlantic Yards Committee asked why this had been excluded from the EIS Mr. Paget said, 'We are not privy to it.'" Because of the conflict he couldn’t be. (BTW: Paget was also working for Ratner on other projects.)

    Edmead found that David Paget’s representation of Ratner and ESDC was concurrent. That Paget’s conflict resulted in a deficiency in the EIS supports this and indicates that the Appellate Division was wrong on the facts when it said that the dual representation (on this specific project) was ostensibly “consecutive” which it used as part of its basis in overturning Justice Edmead.

    If the Appellate Division was correct to say that only ESDC or Ratner had (as per a conventional non-public agency setting) the ability to object to a conflict (inconsistently with the decision not to let Columbia and ESDC hire AKRF at the same time) and that ESDC therefore had the legal right to exercise the bad judgment of waiving the conflict, this does not change the fact that the conflict corrupts the determination being reached and sets up what Baker referred to as “a stacked deck.”

    If actually allowed as became the case, the corrupted process and “stacked deck” should therefore, become an extra basis for challenging the determination (like what happned in the Columbia case). This should be deemed implicitly acknowledged by the Appellate Division’s assertion that the primary reason it was allowing the “appearance of impropriety” of waiving the conflict was that those wanting to challenge the determination “have recourse, . . to provide input into and, if necessary, to obtain judicial review of ESDC's determination.” If that judicial review does not, accordingly, include giving substantial weight to the corruption of the determination by the conflict then that so-called protection is meaningless, especially if there is no diminished deference to public officials despite the corruption.

    For the AYR report on the Appellate Division’s decision see: Saturday, July 01, 2006
    Appeal on disqualification of lawyer challenges ESDC business as usual.
    http://atlanticyardsreport.blogspot.com/2006/07/appeal-on-disqualification-of-lawyer.html

    Michael D. D. White
    Noticing New York
    http://noticingnewyork.blogspot.com/

    ReplyDelete

Post a Comment

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…