Skip to main content

DOT says Ratner may be trying to stretch deadline past three years for completion of Carlton Avenue bridge

So, the first alarming thing about Forest City Ratner's contract with the city Department of Transportation (DOT) to rebuild the Carlton Avenue Bridge was the revelation, as I reported in January, that the developer had three years to complete the job without penalty, even though the Final Environmental Impact Statement (FEIS) produced by the Empire State Development Corporation (ESDC) disclosed the work would take two years.

(Photo by Jonathan Barkey)

Now the developer may be trying to stretch the deadline and thus avoid $10,000 a day penalties. How? A clause in the contract, signed 12/17/07, provides up to five years to complete the work in case of Unavoidable Delay. (Demolition began in January 2008.)

Among the definitions of Unavoidable Delay is a delay in "completing the Master Closing," which is defined as including the ESDC's exercise of eminent domain and the closing of a purchase and sale agreement with the MTA/LIRR for the Vanderbilt Yard.

Neither have been accomplished. And if an arena would not open until 2012, in the best-case scenario, that means Forest City Ratner might want to have four--nearly five--years to complete work on the bridge.

FCR's contract advantage

"They have reached out to us," David Woloch, the DOT's Deputy Commissioner of External Affairs, said at a meeting last night of the Council of Brooklyn Neighborhoods (CBN). "The essence of what's been suggested is that... if there's a delay in completing the Master Closing by the ESDC, that's an Unavoidable Delay."

"So basically what they're saying is, until ESDC takes the land, they're entitled to a time out?" asked Candace Carponter, co-chair of CBN, which was a plaintiff in a lawsuit challenging the environmental review. (Click on graphics to enlarge.)

I heard one "yes" from Woloch's group of four DOT officials, but Chris Hrones, Downtown Brooklyn Transportation Coordinator, said, "We're still working on that."

Legal barriers?

The state eminent domain case dismissed last week, Hrones said, was cited by FCR as "something that prevented them moving forward in their estimation, because it really put the project in doubt."

"Since that court case has been resolved, at least by the Appellate Division, I think we feel like, we'd like to get an explanation why they aren't proceeding," Hrones said, adding that DOT is seeking a meeting with the developer. "We definitely want some answers from them.

Carponter pointed out, however, that, when the demolition began in early 2008, eminent domain litigation had already been filed in federal court. (It was coordinated by Develop Don't Destroy Brooklyn, for which she is legal chair.)

"If that's preventing them now," she said, "it should've been preventing them from taking it down in the first place" and inconveniencing people with a half-demolished bridge.

After all, as I noted last December, FCR officials twice said in court papers:
FCRC’s construction schedule has been carefully drawn to allow the arena to be ready... by commencing work now on vacant properties that are owned by FCRC, the MTA and the City, with work on properties that are owned or occupied by other parties deferred until the pending judicial challenges to the Project have proceeded to a point where ESDC is in a position to actually use its powers of eminent domain to acquire title to and possession of those properties.
(Emphasis added)

Still, the DOT may have only partial leverage. The contract's definition of Unavoidable Delay, noted above, provides "that Developer establishes to DOT that such litigation prevents Developer from proceeding with the Developer Work." 

But there doesn't appear to be such slack in the definition of Master Closing.

"We're going to try, on behalf of the city and on behalf of the taxpayers of the city, to make sure that, given this contract, we get the best deal out of it," Woloch said. "If they come to us and want X months to count as an Unavoidable Delay, and we don't think that's fair, then, we'll push back. We want to get the bridge open as quickly as possible."

Additional delay?

Beyond that, unmentioned at the meeting, there's additional contract language that allows reconstruction of the bridge to take more than five years if the "unavoidable delay directly and specifically precludes the Developer from Substantially Completing the Bridge."

In other words, there seem to be two levels of Unavoidable Delay--one a rather malleable term and one that means what it says.

Failure to communicate

Was the ESDC informed, when the FEIS was produced, about the potential for a 36-month closure?

DOT staffers responded that 36 months was supposed to be an outside bound, since the bridge could be reconstructed within two years.

I followed up: But was the ESDC informed, so it could be disclosed in the FEIS?

"As far as I know, not by DOT," Woloch said. "The negotiation was in the contract with Forest City.... They wanted a cushion."

While that's understandable, and probably not unusual in contract negotiations, the contract came after the FEIS was finished, and ESDC had no oversight role. 

If a post-FEIS contract can trump the information disclosed in the environmental review, what's the point of the ESDC review?

No timetable

Woloch said there's no current schedule for completion of the bridge, but "we have reached out recently" to try to find out.

"As much as some of us don't like this project, we also don't want it to happen badly," Carponter said. "Now, we've got a project we hate that's happening badly."

Fire Department, and notices

DOT officials were asked whether the Fire Department had cleared the closing of the bridge, given that a fire station is nearby on Dean Street. Joe Noto, executive director of the Office of Construction Mitigation and Coordination, said yes, and that Fire Department brass felt confident that response would not be hampered.

"Since the bridge closed, we haven't reached out for updates," he said, "but they haven't come to us" with complaints. Some community members, however, have said individual firefighters have indicated dismay at the closing.

Also, Hrones said that DOT would require five weeks notice before any major street, such as Fifth Avenue north of Flatbush Avenue, would be closed.

Replacement bridge, GPP

Could a temporary replacement for the Carlton Avenue Bridge be built, serving pedestrians and bicyclists? No, the group was told; it would cost $5 million and take two years to construct.

Is the DOT involved in plans to amend the ESDC's Modified General Project Plan, which may be coming in the next month or two? Not yet, the group was told.

Comments

  1. screw the cost.

    lest see


    google is your friend

    seach terms:

    bridge
    temporary
    pedestrian


    on 1st page:

    http://www.bridgeandrail.com/pedestrian-bridges.php


    http://www.bigrmfg.com/products/

    http://www.baileybridge.com/


    http://www.mitchellbridges.com/construction-bridges

    http://www.contech-cpi.com/bridges/products/truss/continental_bridges/341


    and, have costs tripled in the last 5 years?


    http://www.nytimes.com/2001/12/05/nyregion/battery-park-residents-oppose-a-temporary-pedestrian-bridge.html

    ReplyDelete

Post a Comment

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…