From the latest Construction Update: virtually no change, except for some Saturday track work

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, Nov. 25, was circulated Friday at 3:59 pm (lead time) by Empire State Development (ESD) after preparation by Greenland Forest City Partners.

There's virtually nothing new, except for track work noted below.

After-hours work continues

Saturday daytime electrical utility installations, site restoration, and work that requires LIRR track outages are expected to continue in the railyard. In addition, Saturday track work is expected during this time period. (That's next week, not today.)

Excavation work is expected to continue on Saturdays at the B15 and B4 sites from 9 am through 5 pm, through the end of the year.

At the railyard, the LIRR may be utilizing portions of the yard lighting for security reasons. That's "expected to continue for the next several weeks." That could continue for a while.

Weekend work at the railyard, during a second shift from 6 pm to 6 am, will again include excavation, installation of train servicing equipment, and installation of yard lighting structures, and some demolition.

Construction coming

While the B12 and B13 sites are not expected to begin construction until next year, the contractor may again repair parts of the existing construction fence at both sites.