Skip to main content

Why the arena would cost about $900 million--and why the Carlton Avenue Bridge job hasn't been paid for yet

In the Empire State Development Corporation's 2009 Modified General Project Plan, the Atlantic Yards arena was to cost $772 million, but there was also $717 million for project infrastructure as a whole.

Now, according to the Barclays Center Arena Preliminary Official Statement (prepared by Goldman Sachs) states, the arena would cost $904.3 million, including $807.1 million for site preparation costs, hard costs, soft costs and contingency, plus $97.2 million for Arena Infrastructure. Add to that $195 million in Related Infrastructure needed for the arena to open.

That adds up to just about $1.1 billion.

Arena Project $904.3 million

From the document:
Arena Project costs including site preparation costs, hard costs, soft costs and contingency which total approximately $807.1 million and Arena Infrastructure costs total approximately $97.2 million. Total Arena Project costs will thus equal approximately $904.3 million. Of the approximately $904.3 million of total Arena Project costs, approximately $156.5 million has been contributed as of October 31, 2009, which amount includes $85 million in funds received under the City Funding Agreement. As of November 1, 2009, approximately $747.8 million in costs will be required to complete the Arena Project (approximately $655.8 million are Arena costs and approximately $92.0 million are Arena Infrastructure costs). Of the approximately $655.8 million of remaining Arena costs, approximately $481.3 million are covered by the provisions of the Arena Design/Build Contract (exclusive of approximately $3.3 million which has been paid to the Arena Design/Build Contractor). The approximately $481.3 million covered by the Design/Build Contract includes approximately $19.7 million of contingency. Furthermore, there is an additional Arena Project contingency in the amount of approximately $33.4 million. Contracts have not yet been entered into for the construction of the Arena Infrastructure.
Related Infrastructure $195 million

From the document:
In addition to the construction of the Arena Infrastructure, certain other items of infrastructure (the “Related Infrastructure”) will be required in order to open the Arena. Total Related Infrastructure Improvement Costs are projected to be $195.0 million, approximately $94.5 million of which has been incurred as of October 31, 2009 with $100.5 million of which is remaining to be incurred. The costs of such Related Infrastructure are not covered by the proceeds of the Series 2009 PILOT Bonds.

Such work overlaps with that of the Atlantic Yards Project, some of which is in progress and all of which will be performed by AYDC or its affiliates and funded from other sources, including but mot limited to amounts received from the State under the State Funding Agreement. Funds needed to complete the Related Infrastructure will be deposited by AYDC in a trust account, separate from the funds and accounts established under the PILOT Bonds Indenture for the Series 2009 PILOT Bonds, on or about the date on which ESDC acquires vacant possession of the Arena Premises and certain other parcels within the AY Project Site, as described below under “—Infrastructure Trust Agreement.” However, if such funds are not made available at that time, the Series 2009 PILOT Bonds will be subject to extraordinary mandatory redemption as described herein. See “INTRODUCTION—Commencement Agreement” and “THE SERIES 2009 PILOT BONDS—Redemption—Extraordinary Mandatory Redemption.”

The Related Infrastructure will include the following work necessary for the development, construction, equipment and operation of the Arena: construction of a temporary rail yard in order to move most of LIRR operations off of the Arena Premises; excavation and relocation of sewer pipes and water mains from Fifth Avenue and Pacific Avenue to permit construction of the Arena Project and to service the Arena; demolition of existing improvements; environmental remediation, and the rebuilding of the Carlton Avenue Bridge which links Atlantic Avenue and Pacific Street on the East side of the AY Project Site, between Sixth Avenue and Vanderbilt Avenue. Parking to service Arena patrons on a nonexclusive basis will initially be provided on the eastern side of the AY Project Site, on Block 1129 on the Borough of Brooklyn Tax Map (“Block 1129”), to service the Arena. See “ARENA MANAGEMENT AND OPERATIONS⎯Project Leases and Agreements⎯Parking Easement.”
The Carlton Avenue Bridge

Wonder when the Carlton Avenue Bridge would be reconstructed? (It was supposed to take two years but instead would take at least three years.) Well, the money is supposed to be coming.

From the document:
Infrastructure Trust Agreement. The funds necessary to complete the Related Infrastructure will be held pursuant to the Infrastructure Trust Agreement among AYDC, the City and The Bank of New York Mellon, as Infrastructure Trustee (the “Infrastructure Trust Agreement”). The Infrastructure Trust Agreement requires that, at the time of the delivery of vacant possession the parcels that make up the first taking of land within the AY Project Site, including the Arena Premises, (i) $15.0 million be placed in a Bridge Construction Account to be used for costs of the construction of the Carlton Avenue Bridge, and (ii) such funds as are required by the Construction Monitor to complete other Related Infrastructure improvements be placed in an Infrastructure Improvements Account (such account, together with the Bridge Construction Account, the “Infrastructure Fund”). The Infrastructure Trustee will disburse the funds in accordance with the requisition requests made by the Construction Monitor. Pursuant to the Infrastructure Trust Agreement, no requisition requests to draw funds from the Bridge Construction

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

The previous graphic, from August 2017 (without the ghost B1)

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …