Skip to main content

Atlantic Yards paradox, Part 2: the footprint area doesn't count for "neighborhood character," but it sure did for blight

Yesterday I wrote Atlantic Yards paradox, Part 1, observing that Empire State Development's dismissal of a multi-developer alternative to build Atlantic Yards was indeed plausible, but only because the state agency changed the rules, extending Forest City Ratner's deadline from ten to 25 years but leaving a complex series of transactions in place that would be extremely difficult to unwind.

Another paradox shines through the court-ordered Draft Supplemental Environmental Impact Statement (SEIS) issued last Friday, which evaluates the community impacts of a potential 25-year buildout for Phase 2 (11 towers east of Sixth Avenue) and concludes there are relatively few, and most of them can be mitigated.

As in the Final EIS issued in 2006, the Draft SEIS concludes that the blocks around the Atlantic Yards site would experience "significant adverse localized neighborhood character impacts." Now they could extend 18 years rather than six years.

But such "localized impacts would not result in significant adverse neighborhood character impacts in the Prospect Heights neighborhood" and though the delay "would defer temporarily the benefits of Phase II, the benefits would nevertheless improve the character of the neighborhood when construction is completed."

So there's a problem, it will last longer than expected/analyzed, it will all be resolved, and it doesn't matter for the purpose of environmental analysis, because its a "localized" area, but not a neighborhood.

Surely it's a stretch for the state to say that an additional 12 years is merely "consistent" with previous findings. (I've called a similar claim "the meaninglessness of time.")

But the larger paradox is this: when it came time to study blight, the state agency limited itself to the odd map Forest City Ratner chose and deliberately ignored its plan to conduct a market study of property in the surrounding area, which was clearly gentrifying.

In other words, when it came to blight, the larger neighborhood context--which could have demolished the study's conclusions--didn't matter.

When it comes to neighborhood impacts, the larger neighborhood context--in which the impacts can be mostly dismissed--holds sway.

That's called having it both ways.

The blight study

ESD (aka Empire State Development Corporation) asserted, attempting a straight face, "The blighted conditions appear to be limited in large part to the project site itself."

However, as I wrote, that map was highly arbitrary, and clearly expedient.


For example, the site for Building 15, the unbuilt site in the graphic at right, was chosen likely because it could serve as temporary surface parking and staging during the construction of the arena block, Phase 1.

The map included un-blighted parcels but deliberately omitted a vacant lot, which was blighted under the state's definition.

However, because Forest City chose to build only the arena, and decouple the four towers, the site east of Sixth Avenue was not needed. Part of it now serves as a parking lot of TV trucks and other vehicles.
During construction: neighborhood character

According to the Chapter 3L of the Draft SEIS, Construction Land Use and Neighborhood Character:
Construction of Phase II of the Project under the Extended Build-Out Scenario is not expected to result in significant adverse neighborhood character impacts in neighborhoods surrounding the Phase II project site; however, increased traffic, noise, and views of construction activity would result in significant adverse localized neighborhood character impacts in the immediate vicinity of the Phase II project site. During construction, the project site and the immediately surrounding area would be subject to added traffic from construction trucks and worker vehicles and partial sidewalk and lane closures; in particular, construction traffic and noise would change the quiet character of Dean Street, Pacific Street and Carlton Avenue in the immediate vicinity of the project site. In addition, staging activities, temporary sidewalks, construction fencing, and construction equipment and building superstructure would be visible to pedestrians in the immediate vicinity of the Phase II project site... 
These impacts would occur for a longer period of time than what was contemplated in the 2006 FEIS, as the duration of construction activities for Phase II under the Extended Build-Out Scenario would be 18 years, compared with six years in the 2006 FEIS. The impacts would be localized, confined largely to Dean Street, Pacific Street, and Carlton Avenue, and no immediate area would experience the effects of the Project’s construction activities for the full project construction duration. Measures to control noise, vibration, and dust on construction sites, including the erection of construction fencing, would reduce views of construction sites and buffer noise emitted from construction activities, and sound barriers would be used to reduce noise from particularly noisy activities where practicable. However, significant traffic and noise impacts and the effects of views of the construction sites would affect neighborhood character in the areas immediately adjacent to the Phase II project site for a prolonged period under the Extended Build-Out Scenario.
Consistent with the 2006 FEIS, this SEIS finds that construction of Phase II of the Project would not result in significant adverse neighborhood character impacts beyond the significant adverse localized impacts in the immediate vicinity of the project site.
(all emphases added)

During operation: neighborhood character

The chapter on Operational Neighborhood Character comes to similar conclusions:
Consistent with the 2006 FEIS and 2009 Technical Memorandum, this SEIS analysis finds that while Phase II of the Project would result in localized adverse neighborhood character impacts along Dean Street due to increased activity and significant adverse traffic and pedestrian condition impacts, and along Bergen Street due to significant adverse traffic impacts, these impacts would be highly localized and would not result in significant adverse neighborhood character impacts. While a delay in construction of Phase II of the Project under the Extended Build-Out Scenario would defer temporarily the benefits of Phase II, the benefits would nevertheless improve the character of the neighborhood when construction is completed. Overall, Phase II of the Project under the Extended Build-Out Scenario would have a beneficial effect on neighborhood character, creating a vibrant mixed use area, improving the streetscape in and around the project site and knitting together the neighborhoods north and south of the rail yard.
Summarizing the FEIS:
The 2006 FEIS indicated that the Project would result in localized adverse neighborhood character impacts in certain areas closest to the project site. In general, areas of localized impact identified in the 2006 FEIS related to the Phase I development, which is not the subject of this SEIS. However, the 2006 FEIS did identify localized adverse neighborhood character impacts on Dean Street along the southern border of the project site (including the eastern portion, adjacent to the Phase II project site), a street that would change from a nondescript, but quiet, mixed-use (i.e., industrial, commercial and residential) street to an active street with a mix of uses. However, the 2006 FEIS concluded that Dean Street does not possess the attributes and character of the stable residential districts more readily identifiable within the Prospect Heights neighborhood to the south. The core of the Prospect Heights neighborhood is preserved in an historic district (the Prospect Heights Historic District). Residential uses in this district, and most of the neighborhood south of St. Mark’s Avenue and west of Washington Avenue, are found on quiet tree-lined streets characterized by uninterrupted rows of attached two- to four-story rowhouses faced in brick and brownstone that are typically set back from the street and allow for a small front garden. Changes in neighborhood character along Dean Street would not affect the historic residential areas of Prospect Heights.
The 2006 FEIS concluded that the changes to the overall character of Dean Street would not be significantly adverse, and that overall the Project would not result in significant adverse neighborhood character impacts. To the contrary, the 2006 FEIS concluded that Phase II of the Project would further City policies and redevelopment objectives associated with the Atlantic Terminal Urban Renewal Area (ATURA), transforming the project site into a vibrant mixed-use area and knitting together the surrounding neighborhoods which have long been separated by the physical and visual barrier formed by the open rail yard.
Comparing Draft SEIS and FEIS

The document states:
Consistent with previous environmental analyses, this SEIS concludes that operation of Phase II of the Project upon completion under the Extended Build-Out Scenario would not result in significant adverse neighborhood character impacts. Traffic impacts would vary somewhat from those identified in the 2006 FEIS due to a number of factors such as changes in transportation planning factors, travel characteristics of Arena patrons, and updated No Build projects and baseline traffic count. However, the general location and magnitude of impacts identified in the SEIS and 2006 FEIS are comparable as they relate to the character of neighborhoods surrounding the project site. Unmitigated traffic impacts associated with Phase II development under the Extended Build-Out Scenario, coupled with increases in pedestrian activity, would result in localized neighborhood character impacts along Dean Street and Bergen Street, the one-way east-west couplet on the southern boundary of the project site, but these localized impacts would not result in significant adverse neighborhood character impacts in the Prospect Heights neighborhood.
On the contrary, significant neighborhood character benefits would result upon completion of Phase II of the Project under the Extended Build-Out Scenario, in that it would transform the site into a vibrant mixed use neighborhood with eight acres of open space, improve the streetscape and connect the neighborhoods to the north and south of the rail yard. While a delay in construction would defer these benefits temporarily, the benefits would nevertheless improve the character of the neighborhood when construction is completed. These SEIS findings are consistent with those presented in the 2006 FEIS for neighborhood character.
Looking at CEQR

Note that "neighborhood character" is not a colloquial phrase but a section in City Environmental Quality Review (CEQR), the technical manual for which is also used by the state. According to the chapter on Neighborhood Character, it states:
In a neighborhood character assessment under CEQR, one considers how elements of the environment combine to create the context and feeling of a neighborhood and how a project may affect that context and feeling. Thus, to determine a project's effects on neighborhood character, the elements that contribute to a neighborhood’s context and feeling are considered together.
...Neighborhood character impacts are rare. Only under unusual circumstances would a combination of moderate effects to the neighborhood result in an impact to neighborhood character, in the absence of an impact in any of the relevant technical areas.
Moreover, a significant impact identified in one of the technical areas that contribute to a neighborhood’s character is not automatically equivalent to a significant impact on neighborhood character. Rather, it serves as an indication that neighborhood character should be examined. The examination focuses on whether a defining feature of the neighborhood's character may be significantly affected. For example, a significant traffic impact may occur if a project adds ve hicles to an intersection, increasing the delay to unacceptable levels. This significant impact would not constitute an impact on neighborhood character, however, if a neighborhood’s traffic conditions are not considered one of its defining features (i.e., if the traffic conditions are comparable to those of many other neighborhoods and areas in the City).
It states:
To determine whether a Neighborhood Character assessment is appropriate, answer the following question:
Would the project have the potential to result in any significant adverse impacts in the following areas?
  • Land Use, Zoning, and Public Policy;
  • Socioeconomic Conditions;
  • Open Space;
  • Historic and Cultural Resources;
  • Urban Design and Visual Resources;
  • Shadows;
  • Transportation; or
  • Noise.
If “Yes,” a preliminary assessment of neighborhood character may be appropriate. For guidance on conducting a preliminary neighborhood character assessment, proceed to Section 310, below. If the answer is “No,” a preliminary assessment of neighborhood character probably is not required. However, depending on the project, a combination of moderate changes in several of these technical areas may potentially have a significant effect on neighborhood character. See Section 220, below, for further information.
What's the study area?

Interestingly, the manual does note:
Smaller study areas may be appropriate if the neighborhood that may be affected is itself smaller than the typical study area. An example may be a mid-rise (15- to 20-story) building proposed for midblock in a residential part of the Upper West Side of Manhattan and the midblock portion of the block has a strongly defined low-rise (four- to five-story) residential character that is very different from the ends of the block, where mid-rise buildings with ground floor retail front wide avenues. The proposed building may not affect the character of the ends of the block, but may affect the mid-block portion. Therefore, it may be appropriate for the study area to focus on the midblocks. Considering a study area that is too large would dilute the intensity of the effects.
For generic actions that would affect relatively small areas, the affected areas would serve as the study area. When large areas would be affected, the analysis considers neighborhoods typical of those that would be affected.
I'll note that critics who consider environmental review too burdensome would like to see the "neighborhood character" concept eliminated.

Neighborhood vs. sub-neighborhood

The manual notes:
In general, the more uniform and consistent the existing neighborhood context, the more sensitive it is to change. A neighborhood that has a more varied context is typically able to tolerate greater changes without experiencing significant impacts.
There's a logic to that. But that same logic goes to the paradox I identified: were the blighted conditions truly those that might mean, as an urban planner would put it, "the fabric of a community is shot to hell"?

Prospect Heights was not "shot to hell." Nor was the project footprint. But the blight designation was very helpful.

Well, as Brooklyn Legal Services' Marty Needleman told City Council yesterday during a hearing about the plan for the Domino sugar refinery site, "The law's what you can get away with."

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.