Skip to main content

When will the arena open? The goalposts are already shifting slightly, thanks to "current schedule disputes"

When is the Barclays Center arena expected to open?

According to an affidavit from Forest City Ratner executive MaryAnne Gilmartin, arguing against any stay in construction, work is carefully timed so the arena can be finished by the summer of 2012 so it then be "commissioned" to open for the basketball season in October 2012.

However, there are apparently some delays in the schedule separate from any potential delays caused by litigation, as consultants report, detailed below.

It's also unclear when an arena not-yet-commissioned for basketball could open before the season to accommodate concerts (such as for Jay-Z) and other events, though presumably such events are planned and basketball is the most complicated to stage.

The statement, and a precursor

On p. 241 of the file at bottom (p. 30 of Gilmartin's affidavit), she states:
All of the various construction-related activities described above are part of a carefully developed and very intricate sequence of work that is now intended to allow the Barclays Center arena to open in time to permit the Nets to play home games at the Barclays Center by the beginning of the 2012-13 N.B.A. season. Furthermore, it takes several months to commission an arena like Barclays Center--i.e., to test and refine the various building systems and the various operations (such as security and food services) that must be performing properly and efficiently before the arena can be opened for the professional basketball season. In other words, it is essential that the arena be completed by the summer of 2012, so that the commissioning process can be completed by the opening of the basketball season in October 2012.
Of course, in April 2007, Gilmartin's predecessor, Jim Stuckey, said something very similar in an affidavit:
The current work is proceeding in accordance with an intricate schedule that is intended to allow the new arena to be completed in time for the Nets to relocate there for the 2009-10 National Basketball Association season.
Schedule changes?

There are independent eyes on the arena buildout, and while the consultants say the arena is ahead of schedule according to one index, they also acknowledge it's fallen back a month on another measure.

For the last six months, the firm Merritt & Harris, "Consultants to the Real Estate Lending and Investment Community since 1937," has filed reports on the project to Forest City Ratner, the Empire State Development Corporation, and The Bank of New York Mellon, as PILOT Bond Trustee.

The Arena Site Observation Report #5 as of 10/01/2010 (3.5 MB) , at p. 24 (or p. 27 of the PDF), states:
According to the Developer, the project began in January 2010, with initial mobilization by the General Contractor. A Notice to Proceed was executed as of March 15, 2010, with a contractual completion date by July 15, 2012, for a 28-month construction term.
(All emphases added)
Pushed back one month

Both the completion date and construction term seem to have been adjusted, or fallen by the wayside, given "current schedule disputes," as noted below.

The latest, Arena Site Observation Report #7 as of 12/02/2010 (3.3 MB) states on p. 27 (or PDF p. 30):
A High Level Arena Summary Construction Schedule, dated July 16, 2010, has been provided for our review. The current schedule, prepared by Hunt, indicates that substantial completion is anticipated to be by August 12, 2012. The Developer is currently reviewing that schedule and there is a meeting anticipated for mid-December to resolve current schedule disputes.
(The November report said the same thing.)

This suggests that no schedule had been provided until after the October report and that the arena is already a month later than previously expected.

Still, the report still suggests some flexibility:
In our opinion, the construction term of 26 months for the Arena is reasonable, provided that adequate manpower is maintained throughout the construction term, and that there are no hold-ups, such as strikes, inclement weather, material shortages, or other unforeseen circumstances.
This is somewhat confusing, given that the earlier report said the construction term was 28 months.

It's ahead, on another index

The Merritt & Harris report also states:
We are enclosing our own Computerized Construction Chart on which we have plotted actual construction progress versus the projected construction progress (see Attachment). This chart, based on cash flow projections, gives you an idea as to how the project is progressing on a month-to-month basis.

Currently, the project is slightly ahead of schedule.
That's also somewhat confusing. Even as the construction is slightly ahead of schedule based on cash flow, the project's completion date has been pushed back a month.

(Click on graphic below to enlarge and make legible. Note that it's still quite early in the construction process.)

The entire history of Atlantic Yards is delays, so, despite the significant financial incentive to get the arena open by the summer of 2012, it's too early to place definitive bets.
Braun Notice of Cross Motion Affirmation &Affidavit

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.