TRO denied regarding environmental lawsuit; will appeal be expedited?

In an unsurprising decision, a state appellate judge yesterday denied a temporary restraining order (TRO) to block the closure of the Carlton Avenue Bridge sought by the petitioners in the lawsuit challenging the Atlantic Yards environmental review. As part of the appeal of Supreme Court Justice Joan Madden's January 11 decision, the petitioners have asked for a TRO and preliminary injunction to block this "permanent change in the environment of Brooklyn including significant impacts on traffic and significant delays for Fire Department emergency responders."

Should work begin, and petitioners ultimately succeed with their appeal, it's possible that there won't be a working bridge nor adequate funding to reconstruct it, argued petitioners' attorney Jeffrey Baker. Forest City Ratner has argued in the past that any delay increases the cost of the project and delays the expected benefits.

Associate Justice Angela M. Mazzarelli of the Appellate Division, First Department, denied the request, pending a hearing on a motion for an injunction to block the project from moving forward without a final decision on the lawsuit, according to Candace Carponter, legal chair of Develop Don't Destroy Brooklyn. The burden was high, since the petitioners must argue irreparable injury and the likelihood of prevailing on the merits.

"The only way to preserve our rights is to file these motions," she said.

But isn't the issue in some ways moot, given that the TRO was denied, and work on the bridge is supposed to begin January 23? It seems so, but Carponter said maybe not, given that the work has already been delayed a week.

Appeal schedule

Carponter said that the defendants, including the Empire State Development Corporation and Forest City Ratner, will by next Friday file a motion for an expedited appeal, asking that the appellate court arguments be heard in the next few months rather than in September, which Carponter said would be the usual schedule.

The final volley of papers regarding the expedited appeal and the request for a stay is due February 5.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…