Skip to main content

Before hearing today on effort to reopen modular factory, more bitter arguments between Skanska and Forest City

As a hearing this morning approached on Forest City Ratner's lawsuit to reopen the modular factory producing modules for the stalled B2 tower at Atlantic Yards/Pacific Park, more legal filings yesterday detailed the increasingly acrimonious relationship between Forest City and Skanska Building, and their respective affiliates.

(See bottom for an organizational chart of all the parties involved, which include various corporate alter egos.)

Increasing contention

An affidavit from Skanksa's Richard Kennedy details an increasingly contentious relationship regarding blame for the delay in producing modules, including a "vulgar street epithet" from Bruce Ratner:
In early 2014, Skanska Building attempted to engage in constructive conversations with Forest City to resolve issues. Forest City's responses ranged from hostile to inattentive and accusatory. For example, at a meeting on January 28, 2014 when William Flemming, the President of Skanska Building, mentioned that design issues existed, Bruce Ratner's response was to use a vulgar street epithet followed by "I don't care if it costs you fifty million to finish the project ... I'll see you at the grand opening." 
(Did Ratner say "bullshit"--generally termed a "barnyard epithet"--or something else?)

Mike McNally, President of Skanska USA later phoned Forest City CEO MaryAnne Gilmartin, who, according to Kennedy, "was less than pleasant, if not rude." McNally then sent a conciliatory email:
I am very sorry that our conversation went so poorly.
Our team has been focused on finding solutions to increase module production in the factory and have developed several scenarios to complete the project following different production strategies, each of which carries a different anticipated TCO date. It is my understanding that we have shared these with FCR along with the potential financial impact of each scenario.
I believe it is important to state that Skanska wants to continue to work with FCR in a productive and proactive way to tackle the challenges we face and to resolve them in a way that achieves what I believe to be our organizations' common goal of building a successful modular building business and to complete B2 as quickly and economically as possible. And again, I regret our conversation did not conclude on a more positive note.
McNally pointed to "certain root causes" attributable to Forest City, such as an incomplete design for B2, an incorrect estimate of labor productivity, and a flawed module fabrication plan.

While Skanska could, according to its contract, "can stand our ground and insist that all of the costs be paid by FCR," McNally suggested a compromise, aiming to finish the project as quickly and inexpensively as possible.

Thus Skanska would "consider an equitable proposal for funding project costs that will exist through Project completion," then sort out each party's claims. However, according to Kennedy, "McNally's email was met with an aggressive, adjective-filled rebuff the next day."

Next modular buildings?

Beyond the construction questions, Skanska was blindsided by plans announced this past April by the new Forest City Ratner/Greenland Group partnership to build the next towers conventionally.

Kennedy asked Forest City's David Berliner to confirm whether any of the three new residential buildings referenced in a New York Times account were B3 or B4 at the arena site, each mentioned as part of the potential future pipeline in the FC Skanska LLC agreement.

"As you know, B3 and B4 were fundamental to our venture and explicitly formed the basis of Skanska's multi-million dollar investment in our modular business," Kennedy wrote.

But the commitment wasn't firm, given the delay in B2. According to the LLC Contract, the B3 contract for modular construction was predicated on having at least 100 (of 182) of the market-rate units getting leased, that the B3 Owner could get non-recourse financing "on commercially reasonable terms," and the total cost estimate "provides for a commercially reasonable profit for the B3 Owner."

Berliner responded that Forest City was obligated by the Development Agreement signed with the Empire State Development Corporation to start a third building by May 2015, but the delay meant that Forest City was not in a position to evaluate "whether the conditions specified in the Operating Agreement will or can be satisfied," including market-rate units leased, as well as a cost estimate for B3.

"In sum, the delays in the Factory have made it impossible to evaluate, let alone meet, the requirements for awarding it a modular construction contract for B3," wrote Berliner.

He noted that Forest City had promoted modular: "However, with delays that have caused the construction lender for B2 to stop funding, the Factory is not currently in a position to demonstrate such success."

Skanska framed another version of the grievance, citing the Opportunity Brief, as Kennedy wrote:
I am compelled to comment on your characterization below of our FC+S venture as involving a "modular technology experiment". This is a far cry from the definitive representations made by multiple Forest City representatives on multiple occasions over multiple months regarding Forest City's multi-year, multi-million dollar effort that led to it developing the "modular solution" that served as the basis for our negotiations leading to the creation of FC+S and execution of the Atlantic Yards B2 Contract. In this connection I refer you to Bruce Ratner's pronouncement in a November 27, 2012 New York Times article that Forest City had "cracked the code" with respect to modular, Forest City CEO MaryAnne Gilmartin seconded this, saying: "We've cracked a code that will allow us to utilize cutting-edge technology to introduce greater affordability, more sustainability and world-class architecture."
Not only were the factory workers unnerved by the announcement of Forest City's changed plans, so too was supplier Banker Steel "expressing anxiety" regarding Skanska's plans.

"Accordingly, the pipeline of work promised by Forest City in its January 6, 2012 Opportunity Brief and identified in Section 4.1 of the LLC Agreement as part of FCRC Modular's capital contribution to FC+S, no longer appears to exist," Kennedy wrote. (The Opportunity Brief actually refers to both a "pipeline" and a "potential pipeline.")

Losses, and conflicts

Meanwhile, the managers Forest City placed at FCS Modular, "through remiss or intention" did not ask to be paid for additional work caused by design errors or changes, according to Kennedy.

The affidavit, as well as other legal papers, describes a dispute about whether B2 Owner--the entity managed by Forest City--had the resources to fulfill its obligations to Skanska. While Forest City indicated corporate resources, Skanska did not find that acceptable, as no bond as required by Lien Law § 5 was posted.

As Skanska's multi-million dollar loss "continued to escalate," and with no evidence of commitment to pay, it told B2 it would stop work, and then furlough workers, and terminate the Construction Management and Fabrication Services (CM) Agreement.

Skanska and Forest City are in a bitter dispute about whether Skanska was permitted to proceed unilaterally or whether the board of FCS Modular, with three seats for each company had to weigh in.

Reopening the factory?

As noted by the organizational chart, FCS Modular is one of many subcontractors performing work for Skanska Building for B2.

The CM Agreement does not allow B2 to obtain an assignment of Skanska's subcontracts upon a termination for cause, which means, according to Kennedy, that even if Forest City were to prevail and get the current employees back to work while running the factory itself, "there will be no work to perform."

Moreover, Banker Steel, the fabricator and supplier of the chassis/frames, has been directed to stop work by Skanska Building under its subcontract, as have M.G. McGrath, Inc., the façade subcontractor, the mechanical subcontractor and the Simplex system subcontractor.

Skanska suggests there's a remedy: Forest City/B2 could "relet contracts and seek to have FC+S enter into an agreement with the new party constructing the Project... If Skanska Modular declines, FCRC Modular may pursue the opportunity individually, subject to the terms of the LLC Agreement."

Legal arguments

Skanska's lawyers take aim at the affidavits from community supporters of Forest City, writing:
In this third action, Plaintiffs Complaint and current application is long on theater, buyer's remorse and animus, yet short on substance, contractual support or legal precedent. Among the ten affidavits submitted by Plaintiff, nine of those Affiants have no knowledge of any of the facts which are relevant to this action or the two pending related actions. The tenth affidavit from MaryAnne Gilmartin is the subject of substantial dispute.
The alleged "buyer's remorse" refers to clauses in the LLC Agreement that Skanska's lawyers said give them the ability to furlough workers during an "Inactivity Period."

By contrast, Forest City says a "preliminary injunction is needed urgently" because Skanska acted wrongfully and unilaterally:
The Company’s cessation of work, the loss of specially-trained union laborers and the closure of the Factory are irreparably harming FCRC Modular. FCRC Modular is seeking injunctive and related relief to restore the status quo that existed immediately before defendants’ improper conduct.
Forest City says Skanska Building, parent company of Skanska Modular, refuses to accept contractual responsibility for cost overruns, and thus has blamed B2 Owner.

According to Forest City, among the Major Decisions that require Board approval are those that would “effect any material changes in the Business or the strategic direction of the Company that are not specified in an Annual Business Plan approved by the Board.” Instead, the LLC Agreement indicates a  “Deadlock” period and then a “Buy-Sell Option” to buy each other out.

Forest City says the work stoppage "jeopardizes the viability of the Project as a modular building and, with it, the entire business of the [modular] Company.... If B2 BKLYN is not completed as modular construction, the practicality of modular construction, and therefore the need for a modular factory business, will have been called into question."

Skanska has pointed out that, by designating the next buildings as conventional, the practicality of modular construction already has been called into question.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming + FAQ (post-dated pinned post)

This graphic, posted in February 2018, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed--but not yet approved--shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

How many people are expected?

Atlantic Yards/Pacific Park has a projected 6,430 apartments housing 2.1 persons per unit (as per Chapter 4 of the 2006 Final Environmental Impact Statement), which would mean 13,503 new residents, with 1,890 among them in low-income affordable rentals, and 2,835 in moderate- and middle-income affordable rentals.

That leaves 8,778 people in market-rate rentals and condos, though let's call it 8,358 after subtracting 420 who may live in 200 promised below-market condos. So that's 5,145 in below-market units, though many of them won…

The passing of David Sheets, Dean Street renter, former Freddy's bartender, eminent domain plaintiff, and singular personality

David Sheets, longtime Dean Street renter, Freddy's bartender, eminent domain plaintiff, and singular personality, died 1/17/18 in HCA Greenview Hospital in Bowling Green, KY. He was 56.

There are obituary notices in the Bowling Green Daily News and the Wichita Eagle, which state:
He was born in Wichita, KS where he attended public Schools and Wichita State University. He lived for many years in Brooklyn, NY, and was employed as a legal assistant. David's hobby was cartography and had an avid interest in Mass Transit Systems of the world. David was predeceased by his father, Kenneth E. Sheets. He is survived by his mother, Wilma Smith, step-brother, Billy Ray Smith and his wife, Jane all of Bowling Green; step-sister, Ellen Smith Alexander and her husband, Jerry of Bella Vista, AR; several cousins and step-nieces and step-nephews also survive. Memorial Services will be on Monday, January 22, 2018 at 1:00 pm with visitation from 10:00 am to 1:00 pm Monday at Johnson-Vaughn-Phe…

Some skepticism on Belmont hockey deal: lease value seems far below Aqueduct racino; unclear (but large?) cost for LIRR service

As I wrote for The Bridge 12/20/1, The Islanders Say Bye to Brooklyn, But Where Next?, the press conference announcing a new arena at Belmont Park for the New York Islanders was "long on pomp... but short on specifics."

Notably, a lease valued at $40 million "upfront to lease up to 43 acres over 49 years... seems like a good deal on rent for the state-controlled property." Also, the Long Island Rail Road will expand service to Belmont.

That indicates public support for an arena widely described as "privately financed," but how much? We don't know yet, but some more details--or at least questions--have emerged.

An Aqueduct comparable?

Well, we don't know what the other bid was, and there aren't exactly parcels that large offering direct comparables.

But consider: Genting New York LLC in September 2010 was granted a franchise to operate a video lottery terminal under a 30 year lease on 67 acres at Aqueduct Park (as noted by Gov. Andrew Cuomo).

As…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…