The Barclays Center is still on schedule, says Merritt & Harris, construction consultant for the Barclays Center arena bond trustee, which is back to a more regular timetable after skipping two reports in the fall.
The most intriguing element of the Arena Site Observation Report released yesterday, dated 1/16/13 and based on a visit on 11/29/12, was the delayed inclusion of documents regarding belatedly-revealed problems with the arena facade and bolts. (See separate post.)
Nearing completion
The arena is on schedule for final completion of 2/28/13, according to the report, with 102 workers doing punch list work on non-event days.
As of 11/30/12, 97.1% of the budget ($510.7 million) for the arena design/build contract had been spent. Similarly, 97.1% of the budget ($57.9 million) for the transit connection had been spent.
By contrast, only 86.4% of the $3.7 million budget for site work had been spent.
Arena construction progress chart: January 2013 report
(compare with previous charts, based on different elapsed time)
Transit connection construction progress chart: January 2013 report
(compare with previous charts, based on different elapsed time)
The most intriguing element of the Arena Site Observation Report released yesterday, dated 1/16/13 and based on a visit on 11/29/12, was the delayed inclusion of documents regarding belatedly-revealed problems with the arena facade and bolts. (See separate post.)
Nearing completion
The arena is on schedule for final completion of 2/28/13, according to the report, with 102 workers doing punch list work on non-event days.
As of 11/30/12, 97.1% of the budget ($510.7 million) for the arena design/build contract had been spent. Similarly, 97.1% of the budget ($57.9 million) for the transit connection had been spent.
By contrast, only 86.4% of the $3.7 million budget for site work had been spent.
Arena construction progress chart: January 2013 report
(compare with previous charts, based on different elapsed time)
Transit connection construction progress chart: January 2013 report
(compare with previous charts, based on different elapsed time)
Comments
Post a Comment