Skip to main content

What if AY is delayed or smaller? Plausible scenario (25-year buildout, 25% smaller) means projected tax revenues would decline nearly 50%

The Empire State Development Corporation's projected tax revenues (see memo, below) for Atlantic Yards could be cut nearly in half under the plausible conditions--neither of which would incur a penalty--of a 25-year buildout and a project cut 25% in size.

Reasons for doubt

Yesterday, I suggested several reasons to doubt the ESDC's calculations of new tax revenue, which rely on a ten-year buildout of the project. After all, even a supporter such as then-ESDC CEO Marisa Lago said the project would take "decades." The Development Agreement allows 25 years, plus extensions.

Also, the projections rely on a full buildout of the project, nearly 8 million square feet, opening after ten years and continuing for the 30 years. But the Development Agreement allows for a much smaller project, less than 5.2 million square feet.

Full buildout, with delay

Though no alternative calculations or assumptions were provided, a helpful reader prepared a spreadsheet to suggest such alternatives. (The ESDC's assumption of a 3% real discount rate is maintained.)

What if, rather than take a decade to build, the full project took 15 years? That would mean only 90% of projected revenue after 40 years. A 25-year buildout would mean 72% of revenue.

This is actually is a very generous, since delays are most likely to affect the office space, which would be the major driver of revenue, and there's no requirement that the office space be built.

Remember, developer Bruce Ratner told Crain's New York Business in November 2009, “Can you tell me when we are going to need a new office tower?”

And, as I wrote yesterday, the costs are most likely underestimated and there's no effort to explain the calculations.

Partial buildout, with delay

What if only 6 million square feet of the project were completed, a 25% reduction? (Remember, there's no penalty for building even less.) And what if it were delayed?

As the spreadsheet suggests, if for some unlikely reason, 75% of the project were completed in five years, the revenue would exceed 83%. If built in the promised decade, revenue would be 75%.

But a project with 75% of the square footage took 25 years to build, tax revenue would be less than 54%.

Again, that's a very conservative calculation, since delays are most likely to affect the office space, and there's no requirement that the office space be built.

The bottom line

Though there are significant reasons to question the ESDC's effort to calculate costs and benefits, let's look at the calculations for New York City.

The ESDC calculates $834.6 million in benefits for New York City. Multiply that by .5374--the adjustment factor for the 25-year buildout and 25% smaller project--and the total becomes $448.51 million. That's only slightly more than the $389.9 million in costs attributed to the city.

And, as noted, a more rigorous calculation likely would both diminish projected revenues and increase projected costs.

Need for clarity

There's never been a thorough cost-benefit analysis.

In October 2008, Port Authority of NY/NJ Chairman Christopher Ward reported back to Gov. David Paterson on the rebuilding plans at Ground Zero. The Times reported:
To cover his bets, Mr. Ward presented two dates for each project: a target date and a “probabilistic” date, based on computer analysis of all the many random things that might go wrong.

Some “probabilistic” calculations of revenue are surely in order.

Atlantic Yards Economic Impact Analysis 9/17/09

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…