Skip to main content

Atlantic Yards opponents gain procedural edge in court, with arguments delayed until September

The potential timetable for building the Atlantic Yards arena just got pushed back a bit more, with the 2011-12 season now a more likely best-case scenario.

Without explanation, a state appellate court has rejected the request by the Empire State Development Corporation (ESDC) and developer Forest City Ratner (FCR) that the appellate arguments in the case challenging the Atlantic Yards environmental review be heard before this summer. (The decision, dated Feb. 26, was received today by the parties.)

Instead, the five-judge panel of the Appellate Division, First Department, ordered the petitioners, whose case was denied by Judge Joan Madden in a ruling January 11, to file their legal papers by July 7, in anticipation of the court hearing oral arguments in the September Term.

The defendants, as expected, did see the court deny the petitioners' motion for a preliminary injunction to block the demolition of the Carlton Avenue Bridge.

But the court's timetable for the appeal represented an implicit denial of fervent arguments made by the ESDC and FCR.

Arguments for speed

ESDC attorney Philip Karmel had argued, "Delay in construction would delay completion of the Project, postponing it significant public benefits. It is thus critically important that the appeal be perfected so as to be argued before this Court's customary summer recess."

FCR attorney Jeffrey Braun had written, "The issue presented by ESDC's cross-motion is straightforward: Is the public interest in the Atlantic Yards project of sufficient importance to compel the parties to brief this appeal on an expedited schedule that will allow this Court to hear the appeal this spring? The answer to this question is, resoundingly, yes."

Braun continued, "Petitioners make no commitments as to when they will perfect this appeal. Instead, all that they say is this: Currently, it is anticipated that the appeal will be perfected approximately three to four months after the Notice of Appeal was filed on January 18, 2008."

(That would be, at the latest, May 18, 2008.)

"Even if this equivocal non-commitment is viewed as a commitment, it would mean that, at the earliest, the appeal would be heard by this Court during its September 2008 term, which is approximately seven months from now," Braun stated. "This case should not be treated in such a lackadaisical manner."

Braun pointed to the apparent contradiction in the petitioners' asking for what they believe to be sufficient time to file the appeal and the contention that construction work on the site represents irreperable harm: "If the petitioners truly believed that the work was causing irreperable harm, they would be perfecting this appeal expeditiously and pressing for a prompt determination."

Precedent, or evaluation?

The court didn't offer any explanation for its procedural ruling, so it's unclear whether the judges were simply drawing on precedent regarding similar cases or making a judgment regarding the likelihood of the public benefits, given other factors also causing delay, such as the credit crisis and the difficulty in getting bond financing for the affordable housing.

It's not clear how much the timetable has been pushed back. It might take two years to build the arena, once construction starts, but it would be unwise to open the arena until bridges around it have been reconstructed, a three-year process likely not complete until January 2011.

In a best-case scenario, a ruling on behalf of the defendants next fall or winter, would have to be coupled with the U.S. Supreme Court's unwillingness to hear a challenge to the eminent domain case, as well as a dismissal of the emiment domain plaintiffs' effort to bring the case to state court.

That would have to be followed by condemnation proceedings to acquire remaining property and those buildings would have to be demolished.

Nets to Newark?

In other words, the 2011-12 season in Brooklyn may now be the realistic best-case scenario for the opening of the Barclays Center, leaving the Nets three more years in the Izod Center, where crowds have been sparse.

Could Bruce Ratner and fellow team owners be thinking a bit harder about the option of moving--[updated] at least temporarily--to the Prudential Center in Newark? It would cost them a significant penalty as of now, but state officials in New Jersey, thinking they might have a chance of keeping the Nets, might be amenable to negotiation.

Comments

  1. Don't the Atlantic Yard Opponents have a life? Brooklyn if still a city would be the 4th or 5th most populated city in the United States even today. These are the same people who rue plowing pristine rural land or rainforest but heaven help us if someone dares to put density where density and mass transit already exists.

    ReplyDelete

Post a Comment

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

For Atlantic Yards Quality of Life meeting Sept. 19, another bare-bones agenda (green wall?)

A message from Empire State Development (ESD) reminds us that the next Atlantic Yards/Pacific Park Quality of Life Meeting--which aims to update community members on construction and other issues--will be held:
Tuesday, September 19, 2017 @ 6 pm
Shirley Chisholm State Office Building
55 Hanson Place
1st Floor Conference Room
Brooklyn, NY 11217 The typically bare-bones, agenda, below, tells us nothing about the content of the presentation. One thing to look for is any hint of plans to start a new building on the southeast block of the project by the end of the year.

If not, ESD is supposed to re-evaluate a longstanding request from project neighbors to move back a giant wall encroaching on part of Dean Street between Carlton and Vanderbilt avenues. It's said to enclose construction activity, but, in recent months, has significantly served to protect worker parking.

Also, by the way, if you search for Atlantic Yards on Google or the ESD website, it leads to this page for the Atlantic Ya…