Skip to main content

Forest City "generally" in compliance with environmental protocols re Atlantic Yards construction. Locals have their doubts.

Community critics seek increased oversight regarding Atlantic Yards, such as an independent board to ensure fewer violations of construction rules, but the state says everything's pretty much OK.

Chapter 3A: Construction Overview of the Draft Supplemental Environmental Impact Statement (Draft SEIS) issued by Empire State Development, suggests everything's mostly fine, though some improved protocols are coming.

It's tough to take that on faith. For example, it contrasts with the July 2012 report, commissioned by the community initiative Atlantic Yards Watch, that catalogued violations of the Memorandum of Environmental Commitments (MEC) in much detail. And it's been impossible to get records in a timely manner.

It's true changes have been instituted since then, as noted in the Draft SEIS, and there are fewer complaints. But there's also been a lot less construction. The announced changes suggest there was room for improvement.

And though the Construction Overview chapter suggests there are few documented violations, it's tough to trust that. After all, as I reported in July 2012, documents suggest that ESD condoned a cover-up of a Forest City contractor's falsification, as a draft report acknowledging the latter decision was edited to excise such a mention.

The summary

Chapter 3A: Construction Overview contains a lengthy account regarding ENVIRONMENTAL COMPLIANCE AND OVERSIGHT and the role of ESD's technical consultant, Henningson, Durham & Richardson Architecture and Engineering (HDR):
HDR found that the project sponsors were generally in compliance with the requirements set forth in the MEC. In the areas that the project sponsors were not in compliance, HDR noted that prompt action was generally taken to address the non-compliance issues. HDR observed that there were improvements to processes and protocols after construction began, which resulted in improved compliance. The measures outlined in the MEC will continue during Phase II construction. Further, the project sponsors have agreed to incorporate a number of improvements recommended by ESD and HDR to improve the project sponsors’ MEC compliance program. The SEIS analyses presented in the subsequent construction-related chapters examine whether there are additional practicable measures that should be implemented beyond those already required in the MEC for Phase II construction activities under the Extended Build-Out Scenario. ESD will continue to require the project sponsors to implement the required environmental impact avoidance and mitigation measures. During construction of the Project, ESD will also continue to retain the services of appropriate professionals to monitor compliance.
So everything's fine, but there will be some improvements.

What was in MEC?

Some specific MEC components include:
  • MPT [maintenance and protection of traffic] Plans to minimize traffic disruption during construction; 
  • An emissions reduction program, including the requirement to use ultra-low sulfur diesel (ULSD) fuel and diesel particle filters (DPFs) on construction equipment to reduce the air pollutant levels from construction equipment; 
  • A Community Air Monitoring Plan (CAMP) implemented during excavation and other soil disturbing activities; 
  • Remedial Action Work Plans to address contaminated or potentially contaminated soils and materials on the Project site; A noise mitigation program relating to on-site equipment and offering double-glazed or storm windows and air conditioning units to all significantly impacted sensitive uses as identified in the 2006 FEIS (e.g., residential, community facility, houses of worship) to partially mitigate the project’s noise impacts during construction; 
  • Vibration monitoring and Phase 1B archaeological studies to protect historic resources during construction; and 
  • Site-specific rodent control plans. 
Specific elements

Regarding Transportation, the report states, for example, that ten additional speed limit signs around the construction site led to an improvement in compliance with speed limits, while an additional flagger at the entrance of the queuing area prevented trucks from queuing and idling on Vanderbilt Avenue prior to opening of the queue area gates. 

New protocols led to a decrease in idling and a new security guard ensured fewer uncovered loads or inadequate wheel washing. "According to the project sponsors’ records, the Project achieved an average truck protocols compliance rate of approximately 98.8 percent during peak Arena construction," the report states.

While construction workers sometimes illegally parked in non-parking areas, that was reduced thanks to increased NYPD ticketing, "but NYPD would need to remain vigilant in ticketing illegally parked vehicles to keep this issue from resurfacing."

Regarding Air Quality, "[a]ccording to the project sponsors’ records, on average, 98.5 percent of the construction equipment used during peak Arena construction met the DPF [diesel particulate filters] requirement specified in the MEC."

While a Construction Air Quality Measures (CAQM) Compliance Plan was finalized and implemented in April 2010, "HDR observed that a number of the provisions in the CAQM Compliance Plan were not adequately followed, including the submission of the project sponsors’ quarterly environmental monitoring reports in a timely manner, completion of the environmental monitor daily inspection form on a regular basis, and proper training related to the MEC air quality requirements to all contractors working on-site." Follow-up meetings led to some improvements, and more are planned.

Regarding Hazardous Materials, "the project sponsors were generally compliant with the hazardous materials MEC requirements."

Regarding Noise, contractors generally followed Construction Noise Mitigation Plans (CNMPs) but "there were a few instances where violations of the CNMPs were identified, including the use of non-compliant equipment." 

While project sponsors generally "complied with the noise barrier requirement where 8-foot to 16-foot fencing, portable noise curtains, or other means of shielding such as noise blankets were used to reduce noise levels," there was one incident in which a generator and an air compressor were placed at street level near a property line without noise shielding. Since then noise blankets are required.

Regarding Vibration, a monitoring program measures vibration levels at the Swedish Baptist Church and the town houses along Dean Street immediately adjacent to the Project’s Building 15, as well as buildings in the Prospect Heights Historic District within 90 feet of project-related construction activity:
There has been no recorded incident of a vibration threshold exceedance caused by construction activity to date. However, there have been limited instances of vibration threshold exceedances which the project sponsors’ structural engineer has confirmed to have been caused by a local disturbance (e.g., a basement boiler turning on in the building containing the monitor). Based on observation and readings made over the course of Project construction, HDR found that the project sponsors have been in compliance the MEC requirements for construction-related vibration.
Improvements coming

The project sponsors have agreed to incorporate a number of improvements recommended by ESD and HDR, including:
Six-Month Look-Ahead Reports. The project sponsors will provide ESD and HDR reports at regular intervals that describe the activities anticipated on the project site for the next six months.
Contractor Training. The project sponsors will improve the contractor training program by conducting presentations about the detailed requirements of the MEC to all foremen, project managers, field managers, and similar key personnel of all subcontractors upon mobilization, and every 90 days thereafter.
Contracts. The project sponsors will include in their construction contracts, and require their contractors to include in all subcontracts, an exhibit incorporating an excerpt from the MEC that sets forth all construction-related requirements contained in that document. The project sponsors’ construction contracts will expressly require each contractor to comply with all the terms of the MEC that apply to its construction activity, and to require its subcontractors to do the same. The project sponsors will add to their standard MEC-related contractual terms a provision that reiterates the project sponsors’ remedies for a contractor’s non-compliance with the MEC, including the rights to withhold payment or terminate the contract; such provision, however, will be in addition to other remedies available to the project sponsors to address any contractor’s non-compliance with an MEC requirement.
Staffing. The number of OEM [on-site environmental monitor] staff will be adjusted according to the level of construction activity, including any after-hour and/or weekend construction work, to ensure a proper level of monitoring coverage is maintained.
Traffic. Sufficient trained staff will be assigned to oversee compliance with the truck protocols. If any violation is observed, a system will be instituted to facilitate the reporting of violations to the project sponsors. Where a contractor or driver has been found to be a repeat violator of the truck protocols, the project sponsors and ESD will agree on the steps to be taken to deal with the repeat violator.
The project sponsors will ensure that the Pacific Street queuing area between Carlton Avenue and Vanderbilt Avenue will be used to the greatest extent practicable and appropriate, if available.
Maps that identify acceptable truck routes, location of queuing area(s), and construction site access points will be provided to all contractors as part of the MEC training program.
Air Quality. As part of the training program, contractors will be instructed on how to complete and submit documentation needed to confirm compliance with the DPF requirement of the MEC. Where practicable, all equipment that is compliant with the DPF requirement (or equivalent controls) will be prominently labeled.
CAQM Compliance Plan. In 2014, the CAQM Compliance Plan was updated to reference the contractors and personnel working at the project site and to reflect current protocols and procedures. Exhibits to the CAQM Compliance Plan were updated to improve the effectiveness of the CAQM Compliance Plan.
Dust Suppression. A fugitive dust management plan will be prepared for each major phase of work identifying: the location of water supplies, wheel washing procedures, gravel placement, and other pertinent site specific information.
Air Monitoring. Routine inspections of the dust monitoring equipment will be conducted by the OEM to ensure functionality.
Soil Stockpiling. The on-site training PowerPoint presentation for relevant contractors will be updated and improved.
Noise. A written protocol has been developed to confirm that certain “noisier” equipment complies with the noise levels set forth in Table 17c-3 of the 2006 FEIS. All applicable equipment will be checked by the OEM staff either before or promptly upon mobilization to ensure compliance with the MEC noise requirements. In addition, the project sponsors will assure that perimeter fencing meets the requirements of the MEC. Where it is impracticable to meet the noise fence height requirements of the MEC because of site constraints, the project sponsors will install the best practicable sound barriers such as sound attenuation blankets, additional sound barriers, and/or cantilevered fences.
The project sponsors will continue to meet with Con Edison to arrange for the provision of grid power to each building site for use during construction.
Construction staging areas that are located within 200 feet of a sensitive receptor and are used in connection with nighttime work will be shielded (by noise mitigating fencing and/or blanketing) on the side facing those sensitive receptors unless ESD determines that shielding is not required because of the level of anticipated activities and/or duration of such activities.
Comments came first

Note that the Response to Comments document produced by Empire State Development to accompany the release of the Final Scope for a Supplementary EIS contains comments expressing frustration about the state's record, citing the creation of Atlantic Yards Watch to document community impacts and Forest City's inconsistency in providing a construction coordinator.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…