Elected officials will ask DOT to ensure safety at Barclays Center crossing, advise attendance at public meeting tomorrow on scope for Supplemental EIS

A couple of elected officials who long opposed Atlantic Yards still have some specific criticisms, voiced last night at a public meeting sponsored by the Prospect Heights Neighborhood Development Council (PHNDC) at PS 9 on Underhill Avenue. (Here's the live blog from Patch.)

State Senator Velmanette Montgomery said elected officials including her, Council Members Steve Levin and Letitia James, and Assemblyman Walter Mosley, are sending a letter to the city Department of Transportation "to complain about the hazardous crossing in front of the Barclays Center."

"It is so hazardous that one of my staff has reported she was almost killed because a limousine ran one of the yellow lights," Montgomery said. "We've had many, many complaints... we're asking for some remedies."

She added that she's been "extremely aggravated... when I drive up and try to park in front of Atlantic Center and there are these limos running their engines... That's totally unacceptable.. they are waiting for people to come out of the arena and taking up space... the limousines should be sent into the parking lot."

The latter issue has been high on the list of community complaints, while there have been fewer complaints about crossing hazards.

Scoping for SEIS

James invited attendees to attend the first step in the process for a Supplemental Environmental Impact Statement, a public meeting on the Draft Scope of Work for the SEIS, held tomorrow, Feb. 27, from 5-8 pm at St. Francis College, 182 Remsen Street in Brooklyn Heights.

The SEIS was ordered by a state judge after documents unveiled after the 2009 re-approval of the project indicated that Forest City Ratner would have 25 years, not the long-promised ten years and the belatedly studied 15 years, to build the project, but Empire State Development (ESD), the state agency overseeing the project, had not studied the community impacts of such an extended buildout.

"I do not want this district, this borough, to be a construction zone for the next 25 years," James said. "I want promises to be honored... affordable housing... jobs that can sustain families... open space... I want to make sure the development is respectful of the community."

As I wrote in December, the Draft Scope is a first step, intended to draw comments on its "thoroughness and adequacy," either in writing (atlanticyards@esd.ny.gov) and at the public meeting.

After that, a Final Scope will be issued. Then the ESD's consultant, the ubiquitous AKRF, will produce a Draft SEIS. If the pattern from 2006 recurs, that document will be the subject of public comment and a public hearing before a Final SEIS is issued and approved by the ESD board.

The stated goal: to identify any impacts not previously identified and to target potential mitigations.

Though the process likely will lead to few changes, it could raise some contentious issues, such as the delay in removing blight, the impact of delayed (and modular) construction, and whether alternative developers should work alongside Forest City Ratner.

Affordable housing

James said the part of the project she most liked was affordable housing, but "then they did a bait and switch," emphasizing studios and one-bedroom units rather than promised family-sized units. 

She also said, in reference to plans for affordable housing in Crow Hill, that she emphasized housing that served families earning $30-80,000 a year.

From the Fifth Avenue Committee

A press release:
Make Your Voice Heard on the Atlantic Yards Project!
Ensure that Promised Affordable Housing, Jobs and
Open Space become a reality now and not in 25 years
 
Did you know that Forest City Ratner Corporation (FCRC) is not planning on building the vast majority of promised affordable housing for 25 years? Will anyone in the community who qualifies for that housing still live here in 25 years who is now being displaced?

This Wednesday, February 27, the New York State Empire State Development Corporation (ESDC) will hold a public hearing to hear testimony on the draft scope of work for the Atlantic Yards Supplemental Environmental Impact Statement (SEIS). ESDC was ordered to perform the SEIS as a result of a lawsuit brought by Fifth Avenue Committee and several of the other BrooklynSpeaks organizations. The court found that ESDC's 2009 approval of a modified project plan for Atlantic Yards violated State environmental law by extending the construction schedule from ten to twenty-five years without required environmental review.
We have since called for a new plan for Phase 2 of the project, which stretches from 6th Avenue east to Vanderbilt Avenue, which would restore the original project schedule, and deliver public benefits like affordable housing, open space and jobs in the ten years originally promised. The draft scope (available from ESDC's web site) does not include an analysis of such an alternative.
We strongly encourage you to attend and to share your concerns and questions about phase 2 of the project.
The lawsuit combined two lawsuits, one by BrooklynSpeaks members (and elected officials), the other by Develop Don't Destroy Brooklyn and associated groups.

It's hardly clear that Forest City would wait until the last of the 25 years to deliver most of the housing. If the modular plan works, the process would likely be more steady--though the developer plans to build over the surface parking lot before building an expensive deck over the Vanderbilt Yard, thus delaying the plan to remove blight, a main ostensible justification for the project.

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…