At Atlantic Yards, the project's centerpiece basketball arena is nearing completion. But developer Forest City Ratner Cos. has yet to begin any of the 6,400 units of housing it once anticipated being built by 2016—2,250 of which would be for low- and middle-income families. Forest City has cited higher than expected costs and an inclement market, although it plans to break ground this year on its first building with 175 below-market rate units.

The delays have frustrated officials and given fuel to critics of the project, which went through a contested public approval process before the recession.

"They should do the affordable housing up front, now," said Assemblyman James Brennan of Brooklyn, who said the low- and middle-income housing aspects should be accelerated. "The only legitimate selling point for the entire project was the affordable housing."
Unmentioned, however, is the state agreed to give Forest City 12 years to build the first three towers and 25 years for the whole project, despite projections that the 16 towers would be finished in a decade.

The meaning? Bumps in the road or lies on the way?

According to the Journal, the "delays speak to broader challenges of building housing that is affordable to low- and moderate-income families in New York, once the main focus of Mayor Michael Bloomberg's housing agenda."

Well, yes, and no. The delays also speak to the willingness of the state to commission a dubious report from KPMG claiming that the project could be built in a decade, and the willingness of a now-retired Empire State Development Corporation official to dismiss the Kahr report, commissioned by community groups, that was far more pessimistic.

Forest City's commitment

The Journal reports:
At Atlantic Yards, the large number of affordable units—more than one-third—helped Forest City Ratner sell the project to elected officials and some community groups.

"That is of course what we're committed to doing at Atlantic Yards," MaryAnne Gilmartin, executive vice president at Forest City Ratner, said in an interview. "But it turns out not to be so easy."

The company plans to break ground on its first building before the end of the year, a date that has been pushed repeatedly. If the company doesn't start construction by May 2013, it must pay the city $5 million.

Unlike many low- and moderate-income housing developments, Atlantic Yards plans to use union labor, is being built in high rises, and has hundreds of millions of dollars in costs to acquire land, all of which make the development more expensive and challenging, Ms. Gilmartin said.

"We're really trying to do something that isn't something that's been done on a large scale in the city before," she said.
Of course, that project is exactly what was vetted and approved by the state.

Unmentioned is Forest City's plan, officially announced last November, to use risky/innovative modular construction at heights not previously attempted. Has Forest City given up on that?

At least the Journal points out that the start date for the first building "has been pushed [back] repeatedly." In January, I counted about ten times that the goalposts had been moved, with the timing "spring or summer." After that, the start was delayed until after the arena opens, and possibly early next year.

Note that the $5 million penalty kicks in if the building doesn't start by next May, but Forest City Ratner can gain a one-year grace period if it can certify a denial of city housing subsidies.

The Bloomberg record

The Journal's Eliot Brown summarizes the mayor's affordable housing record:
In 2005, Mr. Bloomberg called for building about 92,000 units of so-called affordable housing and preserving 73,000 units in which affordability programs were expiring.

But the city has shifted to preserving units—a tactic many housing advocates say is also needed. New construction is now likely to be roughly one-third of that total of 165,000 affordable units, said Mathew Wambua, the city's housing commissioner.
Earlier this month, the New York Times has reported, erroneously and generously, "On [City Planning Commissioner Amanda Burden's] watch, the administration has undertaken financing 165,000 units of affordable housing by 2014, of which more than 130,000 have been built...."

The phrase "been built" implies construction from the ground up, rather than preservation. No correction has yet been posted.




Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.