AY ten-year timetable realistic or p.r. scheme? ESDC, residents battle in court

The Empire State Development Corporation (ESDC) has filed legal papers asking for a state court to dismiss the lawsuit filed April 30 that charges that the ESDC’s willingness to give developer Forest City Ratner 12+ years to build Phase 1 of Atlantic Yards violates a provision of the Eminent Domain Procedure Law (EDPL). The suit also requests a new public hearing to evaluate the benefits of the amended project.

In arguing against the lawsuit, filed by 13 residential tenants in two buildings within the project footprint, the ESDC curiously claims that the courts should view Bruce Ratner’s May 4 Daily News op-ed asserting a 2018 completion date as more credible than his interview in the March 21 New York Times regarding the project’s stall, and that the penalties facing the developer for delaying the project are “draconian.”

Ten-year timetable realistic?

While the lawsuit, filed on behalf of petitioners who have lost two other suits filed by attorney George Locker, attempts to break new legal ground and thus must be seen as an uphill effort, it brings an important public policy issue to the legal arena. At essence is whether the project approved by the ESDC in December 2006, with a ten-year “anticipated” timetable for an arena, 16 towers, eight acres of open space and more, remains realistic.

The ESDC says it is: “Petitioners cite an exhibit to the [State] Funding Agreement that describes the draconian contractual remedies that would be available to ESDC if FCRC fails to complete established Project milestones by certain outside dates. The fact that ESDC could bring to bear certain contractual remedies in such circumstances does not change the Project approved by ESDC on December 8, 2006. Moreover, a change in the construction schedule would not be the type of significant change in public use that would require a new EDPL public hearing.”

However, the funding agreement does not address a starting or ending date for the 11 towers of Phase 2, instead leaving that to be resolved in yet-unfinished “Project Documentation.” The petitioners thus contend that the ten-year project “that was studied and approved by ESDC in December 2006, as having sufficient public purpose and public benefit, ceased to exist on September 12, 2007, when by agreement AYP [Atlantic Yards Project] became an uncertain project of an unspecified duration.” The petitioners charge that the agreement “was kept hidden from petitioners and from the public for six months.”

While the deadlines may be a “contractual remedy,” Locker’s legal affirmation states, “these descriptions are public relations jargon, not legal analysis. By agreement, a ten-year AYP has become an amended-AYP of unlimited duration.” Moreover, “The amendments represent an enormous loss of the Project’s stated public benefits--most of the housing, open-space, and construction job/years--and portend decades of developer blight, vacant lots, and ever-mounting public costs.”

The project, as approved, “might have been financially unrealistic from its inception,” Locker states. "Respondent’s 10-year [project] is a public relations and marketing scheme; it does not exist in a legally enforceable form.”

ESDC: under negotiation

An affirmation by ESDC lawyer Philip Karmel explains that “Project Documentation” has not been finalized and remains under negotiation; the term refers “to the real estate, financing, construction and other contracts involving ESDC, FCRC, and the City of New York that are required to effectuate the [General Project Plan].”

While Locker included as an exhibit the March 21 Times article headlined Slow Economy Likely to Stall Atlantic Yards, the ESDC objected to the article’s admission because “the purported quotations from Bruce Ratner are pure hearsay as to ESDC,” the statements do not represent ESDC policy, and the article post-dates the September 2007 Funding Agreement challenged in the lawsuit.

“If and to the extent that [the article] is considered,” Karmel adds, “however, it should be noted that Mr. Ratner has made other recent statements concerning the Project--most notably, in his recent article in the Daily News--that shed light on the statements he is quoted as having made to the New York Times.”

In other words, an op-ed from Ratner trumps an interview.

ESDC: claims fall short

In a legal memorandum, the ESDC argues that Locker’s lawsuit fails to state a cause of action because the provision of the EDPL at issue applies only when the condemnor has already acquired the property by eminent domain, the project has been abandoned, and the condemnor seeks to sell the property within ten years of its acquisition. None have occurred.

Further, the EDPL requires that the property be “materially improved” within a decade after acquisition, and the ESDC states there’s no assertion that it wouldn’t be improved, since the term does not require completion of a project.

Further, the response argues that the petitioners do not have any ownership rights and thus lack standing to sue--a claim that raises questions about a previous lawsuit. Locker responds, “ESDC is walking on thin ethical ice by arguing that petitioners, who were determined to be condemnees at ESDC’s legal urging in a previous action, possess standing to assert rights under EDPL section 207, but lack standing to assert the rights accorded to all condemnees under EDPL section 406."

New public hearing?

The petitioners in the latest case also claimed that the EDPL requires a new public hearing “because the Funding Agreement allegedly changed the GPP [General Project Plan] construction schedule,” the ESDC response states. “The Funding Agreement, however, explicitly requires FCRC to use commercially reasonable efforts to achieve the GPP construction schedule.”

Even if the Funding Agreement had modified the construction schedule, the ESDC argues, construction delays on complex public projects are “hardly uncommon,” so if every delay were to require a new public hearing, eminent domain “would cease to serve the role intended by the legislature when the statute was enacted.”

Indeed, the ESDC cites a case involving Times Square redevelopment in which the Court of Appeals rejected the idea that new hearings were required “because the passage of time had rendered stale the data upon which ESDC had relied to make its blight and environmental findings for the project.” Only when there’s a significant change in public purpose is a second public hearing “potentially required,” the ESDC states, and there’s been no such change in public purpose alleged.

In response, the petitioners include an affidavit by Tom Angotti, professor in the Hunter College Department of Urban Affairs & Planning, who notes that Atlantic Yards was always presented as a ten-year project, with the financial, environmental, and infrastructural, analyes predicated on that timetable. Given that there is no stated commencement date nor completion date for the 11 buildings of Phase 2, which would contain an estimated “70% of the affordable housing units, 100% of the open space, and 75% of the construction job/years,” the ESDC should precisely describe the project and hold a public hearing where the public can comment on the “costs and benefits of the amended project,” Angotti states.

"Draconian" remedies?


The ESDC, in its legal papers, calls the contractual remedies cited in the lawsuit “draconian.” The term is doubly curious because the State Funding Agreement cited in the lawsuit describes the penalties incompletely, leaving any analysis inconclusive without a look at the separate City Funding Agreement. That agreement, released later after a Freedom of Information Law request, spells out some provisions that, to my mind, don't seem very draconian, given that the developer need build only 1.5 million square feet over 12 years to escape penalties.

Beyond those remedies, the ESDC states, “it is expected that the Project Documentation will provide for additional remedies available to ESDC in other circumstances.” The contractual remedies, the agency claims, “do not modify the Project schedule.”

Moving ahead

The ESDC further argues that the State Funding Agreement, rather than retard the project, accelerates infrastructure work because it allows work to proceed before Project Documentation is finalized. Even if the developer defaults completely, that would not mean abandonment by ESDC, which could continue the project with another developer. In other words, the ESDC contends, it’s the condemning agency, not the developer, that must abandon the project.

If the motion to dismiss is denied, the ESDC argues that, if the schedule-related provisions of the Funding Agreement were determined to violate the EDPL, the court should annul specific provisions rather than annulling the Funding Agreement as a whole or requiring a public hearing.

The petitioners respond, “ESDC wisely contemplates losing the instant motion and asks this Court to ‘annul any offending portion’ rather than order a hearing, etc. It is unclear how this Court may alter the completion dates of a $4 billion construction project when one of the parties to the agreement is not even before the court and there is every reason to believe that FCRC could not comply. If ESDC wishes to have a ten-year AYP construction deadline imposed on FCRC, as law requires, ESDC should do so on its own.”

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.