The Times mangles the modular story: only part of the battle over B2 is over

OK, it's not the biggest article in the Atlantic Yards saga, but it's notable how the New York Times mangled  Forest City Ratner Buys Out Partner in Brooklyn Residential Tower , which was published online yesterday and is not in today's paper. I suspect that reporter Charles Bagli, who was busy writing an unrelated longer article for today's paper, was given a brief amount of time to write the Brooklyn story, and nobody cared to get it right. The lead: The battle over one of the slowest moving residential towers in New York City’s history is over. No, not at all. Just the battle over control of the factory producing modules for B2. The dueling lawsuits over cost overruns continue. The article continues: But it may be weeks before work resumes on the modular building, which rises only 10 of its intended 32 floors at the corner of Sixth Avenue and Dean Street in Brooklyn , 24 months after work began. It is the first residential building at Forest City Ra...

Updated: Atlantic Yards informational update on agenda for ESD meeting tomorrow (now with memo)

At the end of a rather long agenda for tomorrow morning's board meeting, Empire State Development, the state agency overseeing/shepherding Atlantic Yards, will tackle "Atlantic Yards Informational Item – Update on Status of Project." Presumably that will include the planned groundbreaking for two towers as well as the emerging Atlantic Yards Community Development Corporation. Details Thursday, November 20, 2014, at 9:30 am Where: Empire State Development 633 Third Avenue – 37th Floor Conference Room New York, New York 10017 This meeting is open to the public. Web casting of the meeting will be available . Due to 633 Third Avenue building procedures, those attending in New York City please RSVP by 5:00 pm today. Members of the press call (800) 260-7313; Members of the public call (212) 803-3794. Below is the one-page memo in the board materials . It notes that groundbreaking for the next affordable tower is expected to be in December. The Atlantic Yards ...

Statement: Forest City buys out Skanska's share of troubled modular factory

As I wrote , Forest City was on the verge of buying out Skanska's share of the troubled modular factory at the Brooklyn Navy Yard and thus presumably/potentially restarting production of modules for the stalled B2 tower at Dean Street and Flatbush Avenues. And today it happened. A joint statement today from Forest City Ratner and Skanska: Today FCRC Modular, LLC and Skanska Modular LLC announced that FCRC Modular, LLC will purchase the ownership interest of Skanska Modular LLC in their jointly owned modular factory business in the Brooklyn Navy Yard, FC+Skanska Modular, LLC, for an undisclosed amount. The agreement, achieved through mediation with Roger J. Peters, Esq., marks the end of the companies’ partnership at the modular factory and makes FCRC Modular the sole owner and manager of the modular business. Litigation between the companies over the B2 Project will continue and is not impacted by this agreement. That litigation involves some $50 million in claimed damages...

Was Forest City's Gilmartin appointed to WNYC board because of "passion for public radio" or fundraising help?

So, why was Forest City Ratner CEO MaryAnne Gilmartin appointed to the board of WNYC? As shown in the press release cited by Noticing New York's Michael White, WNYC President and CEO Laura Walker, commenting on the appointment of Gilmartin and three others, said they "bring vast experience in business, media and non-profit governance that will advance both the work of the Board and the mission of New York Public Radio.”   Meanwhile, Cynthia King Vance, Chair, Board of Trustees, New York Public Radio, said “These accomplished leaders bring a passion for public radio and new and valuable perspectives to a highly engaged Board of Trustees." Well, now. I bet it has more to do with raising money. How much may this harm WNYC in credibility? The jury is still out. Forest City has a passion for shaping perception--such as the erasing-history effort to rename Atlantic Yards as Pacific Park .  So even the capsule biography of Gilmartin, surely supplied by her office for t...

At hearing on bonds for new tower, Forest City executive speaks "with great excitement for the future of affordable housing in New York"

There was nothing new beyond rhetoric at the very brief hearing segment yesterday devoted to tax-exempt bonds for 535 Carlton Avenue, the next building in Atlantic Yards/Pacific Park to break ground. After all, a fact sheet (below) had already been distributed with details about the project, including the request for up to $73 million in tax-exempt bonds, which save the builder significant sums compared to conventional financing, and are part of the financing for affordable units. Forest City Ratner VP Melissa Burch, representing Greenland Forest City Partners, led off her brief statement but saying, "It is with great excitement for the future of affordable housing in New York that I present 535 Carlton Avenue at Pacific Park." It's curious that Forest City is flogging this tower--in which half the units would go to middle-income households who'd pay some $3,000 for a two-bedroom unit--as "the future of affordable housing." Also, Burch noted that, ...

Rain and open windows on B2 modular tower

It rained yesterday. So why have windows on the B2 modular tower been left open? (Other modules have panels, or temporary sheeting.) Even if everything inside is wrapped in plastic, that can't be good.

Greenland claims U.S. projects funded via EB-5 have "created 20,000 jobs" (!?!)

The Wall Street Journal reports, in  China’s Greenland Group Expects Overseas Revenue to Double in 2015: Company the Most Aggressive Chinese Property Developer to Expand Abroad Since 2013 : SHANGHAI—Chinese state-owned conglomerate Greenland Holding Group said Monday it expects to reach its targeted 20 billion yuan ($3.27 billion) in overseas revenue this year, and that its overseas revenue will double in 2015. Shanghai-based Greenland has been the most aggressive Chinese property developer to expand abroad since 2013, investing a total of $20 billion purchasing land and other real-estate projects in nine countries including Australia, the U.S., the U.K., Canada and South Korea. Greenland, which isn’t listed on the domestic stock exchange, said it is targeting its overseas revenue to make up a larger portion of the company’s revenue, to exceed 25% of its revenue by 2020.... “In the U.S. for example where our development projects are funded by EB-5 visa funding, preliminary ca...

A meeting today on tax-exempt bonds for next tower; Quality of Life meeting Wednesday features architects of new towers

As I wrote , there's a public hearing today on tax-exempt bonds for 535 Carlton, built at the corner of Carlton Avenue and Dean Street, the first tower to be built by the Greenland Forest City Partners joint venture (and the first under the name Pacific Park Brooklyn), with 298 subsidized apartments. The hearing, which also will cover applications for numerous other tax-exempt bond requests, will be at 11:30 a.m. in the main Conference Room of the New York City Housing Development Corporation (NYC HDC), 110 William Street , 10th Floor, in Manhattan. (It will also be webcast and on toll-free phone.) Quality of Life meeting Wednesday Also, a notice from the Dean Street Block Association notes that architects some project towers are expected at the Quality of Life meeting on Wednesday: Please attend the upcoming Atlantic Yards Quality of Life Meeting for information, or if you have questions about the significant changes to our neighborhood anticipated to start in weeks. It is ...

Discounts for Nets games and college hoops via LivingSocial

Via LivingSocial The Barclays Center doesn't like to talk about discounting, but it offers actually offers discounts on a lot of platforms. Consider the following two discounts via the deal platform LivingSocial. Tickets to Brooklyn Nets games versus the Miami Heat and Chicago Bulls were apparently jacked up too much . So now they're on a significant discount, from 24% to 37.5% for the cheap seats, and 26% to 35% (plus a $75 credit at the 40/40 Club) for the more expensive seats. Keep in mind that, according to various accounts , Living Social takes 40% of the sale price, so the Nets actually reap far less than the discounted ticket price. Via Ticketmaster The Progressive Legends Classic Tickets to the Progressive Legends Classic on Monday, November 24 or Tuesday, November 25 are 46% off, at least if you think $76 is a reasonable face value for college hoops. Actually, they're selling seats directly for $15 (plus service charge, as noted at right),...

Forest City seems ready to buy out Skanska's interest in closed modular factory; deal could close tomorrow

Forest City Ratner seems ready to buy out former partner Skanska from its share of the troubled, shuttered factory at the Brooklyn Navy Yard that was producing modules for the stalled B2 tower at the corner of Dean Street and Flatbush Avenue. That deal--between the companies' modular subsidiaries--presumably would hasten the process to re-start the factory and resume construction, which has reached only ten of 32 floors. The two partners, who've filed a total of three lawsuits, blame each other for delays and cost overruns in the tower. Skanska, which as manager of the factory  shut it down  in late August, on 9/23/14  terminated the overall contract to build B2, including the purchase order for the modules. The reopening of the factory presumably could resolve one lawsuit, but the other two--regarding who should pay for the cost overruns--are on a schedule  requiring papers to be filed by 12/9/14. Deal closing tomorrow? A letter dated Thursday, 11/13/14, ...

Belated notice: for two years, a 16-foot fence plus sidewalk closings at Block 1129 to accommodate construction

Late yesterday afternoon, the developers of Atlantic Yards/Pacific Park Brooklyn sent a Community Notice indicating major changes would begin next Thursday, lasting two years, to accommodate construction on the southeast block of the project site, including a 16-foot high fence aimed to dampen noise and the closing of sidewalks around the perimeter of the site. The notice was headed, not inaccurately but somewhat incompletely, "Temporary Changes to the Roadway Network on Carlton Avenue, Vanderbilt Avenue, and Dean Street." None of the changes were hinted in the two-week Construction Alert sent this past Monday. Note that, while the next tower to start, at 535 Carlton Avenue (the southwest corner of the block), is supposed to open in the fall of 2016, according to a fact sheet distributed by the New York City Housing Development Corporation, the text of the notice states that the "fence around the entire block will remain in place for approximately 24 months." ...

OK, the first of 40 steel deliveries during overnight hours might begin Sunday night. Over what period of time? Stay tuned.

Last Monday, when I got a copy of the latest t wo-week Atlantic Yards/Pacific Park Construction Alert , I thought an ambiguous statement about steel deliveries for the Barclays Center's planned green roof deserved clarification: Steel installation has commenced, with large steel truss deliveries slated to commence November 17th. Deliveries will be made to both the B3 and Atlantic Avenue crane locations. Deliveries to the B3 crane location will be staged on the Dean Street and 6th Avenue sidewalks. Given that they are oversized loads, deliveries of the large steel trusses will be made during overnight hours in accordance with DOT regulations.  So I  followed up with a question to Empire State Development, the state agency issuing the document, which is first prepared by Greenland Forest City Partners: How many deliveries (min-max) are expected per week (or night), and for how many weeks? Is this Sunday overnight through Thursday overnight (for work M-F) or are Friday and S...

Daily News hyperventilates about royal couple's visit to Barclays Center (to see LeBron)

Three--count 'em, three--New York Daily News reporters were required for yesterday's breathless report, Prince William and pregnant Kate Middleton set to see Brooklyn Nets take on LeBron James, the Cleveland Cavaliers: The royal couple will head for the Barclays Center to see the game when they are in New York for three days next month. A selection of the perfectly chosen/delivered quotes: “How befitting for the future King of England to travel to Kings County!” said Borough President Eric Adams, thrilled by the impending arrival of both Cambridge and Cleveland royalty. “So it’s nice that he’s coming to Brooklyn,” said Debra Bock-Woo, 62, who lives near Barclays Center. “I hope they enjoy themselves. It might be their first basketball game.” “That’s so cool,” [Barclays worker Collis Matthews] said Friday. “That’s going to bring a lot of attention here. It’s good for them to come have a little fun. A lot of people are going to want to see ’em. “It’s a good thing,” said Br...

Before hearing on housing bonds Monday, a fact sheet on 535 Carlton tower (298 subsidized units)

There will be a public hearing on Monday, 11/17/14 on tax-exempt bonds for 535 Carlton, built at the corner of Carlton Avenue and Dean Street, the first tower to be built by the Greenland Forest City Partners joint venture (and the first under the name Pacific Park Brooklyn), with 298 subsidized apartments. More of them are family-sized than the first tower but the configuration disproportionately emphasizes middle-income units. The amount of bonds, $73 million, is less than the $92 million sought for the larger B2 tower, which had half market-rate units. The hearing, which also will cover applications for numerous other tax-exempt bond requests, will be at 11:30 a.m. in the main Conference Room of the New York City Housing Development Corporation (NYC HDC), 110 William Street , 10th Floor, in Manhattan. (It will also be webcast and on toll-free phone.) The public is allowed to make comments and, while they surely are noted by staff, they do not--based on the experience with th...

Wrestling personality Noelle Foley, after being denied entry to Powerhouse 2014 show at Barclays Center: "I want to, like, punch your building"

It turns out that the decision by the Barclays Center to close entry  to the  to Powerhouse 2014 hip-hop show on Thursday 10/30/14, made after a "mob" rushed the entrance, pissed off more than a few people, including one with a big megaphone, Noelle Foley, who's the daughter of famed wrestler Mick Foley. First she (and her father) tweeted their dismay, and yesterday she took it to a new level. Seriously @barclayscenter ? I had floor seats to #POWERHOUSE2014 and you're going to deny people at the door? That's complete BS. Ridiculous. — Noelle Foley (@NoelleFoley) October 31, 2014 I used to love @barclayscenter , now I hate @barclayscenter . — Noelle Foley (@NoelleFoley) October 31, 2014 What will be done to correct the @barclayscenter @Power1051 #POWERHOUSE2014 travesty? Ticket-holders denied entry. Insufficient security. — Mick Foley (@realmickfoley) October 31, 2014 Watch me cut a first ever promo on Barclays center for #RingsideOrRiot @Rings...

Forest City seeks "Vice President of Development (Atlantic Yards)." But not Pacific Park?

A reader pointed me to the following job advertisement for Vice President of Development (Atlantic Yards)  posted by Forest City Enterprises for its Forest City Ratner subsidiary. The search for a new staffer for Atlantic Yards--even if, as I highlighted below, the person will work on other projects--suggests that, yes, they're ready to ramp up. And that the ascension last year to CEO by MaryAnne Gilmartin left a job to be filled. I don't know how long the job notice has been posted, so it's possible that it's been up since before they changed the project name to Pacific Park Brooklyn . But you'd think they'd want to update it. Similarly, it may be have been posted before the joint venture with Greenland Holdings, creating Greenland Forest City Partners, began, but it does seem a bit remiss not to update it to tell the new VP he or she might ultimately be answering to (people working for) the government of Shanghai. Vice President of Development (Atl...

Crain's offers softball interview with Greenland USA leader: EB-5 "improves the employment rate"

Crain's New York Business has published an unsurprisingly gentle interview with I-Fei Chang, who leads Greenland USA, the U.S. arm of Greenland Holdings, "a partially state-controlled, Shanghai-based development conglomerate with more than $50 billion in assets," that has bought a 70% share in the Atlantic Yards/Pacific Park project going forward, excluding the Barclays Center and the stalled B2 modular tower. (No, the Brooklyn project is not located "in Fort Greene" but rather Prospect Heights. Chang says Greenland came to the U.S.--it also has a project in Los Angeles--because "It's all about good timing" and "We believe in investing in cities in transition." OK, sure, but maybe it also has something to do with wanting to make a splash internationally and moving money from China, where the real estate market may be more volatile, to more stable markets where a decent return is likely. Also, while Chang says "We're here...

Timetable for modular lawsuits gets stretched out; battle over disqualifying law firm

According to documents filed with the state Supreme Court, the various parties in the dispute over the stalled modular factory run by affiliates of Forest City Ratner and Skanska have agreed to an extended timetable regarding their three lawsuits. In the case related to the shutdown of the modular factory, and whether Forest City can unilaterally reopen it, the parties have until 12/22/14 to file papers. In the cases related to the responsibility for the cost overruns, the parties have until 12/9/14 to respond to each other's legal filings. Battle over disqualification Meanwhile, today the case is scheduled to go before a judge on a related matter: the attempt by Skanska to disqualify the firm Troutman Sanders from representing Forest City in the modular dispute, as Troutman represents another part of Skanska's family of businesses. Skanska earlier denied Troutman a requested waiver to proceed. (Here's a summary from Law 360 based on a preliminary set of legal paper...

Changes to intersection of Atlantic and Sixth, including one-way traffic on Sixth, require two nights of overnight work starting Tuesday

Starting next on or around next Tuesday, 11/18/14, the work on the arena green roof and west portal for the Vanderbilt Yard will require several temporary changes to the roadway network, as well as two nights of overnight work, according to the developers of Atlantic Yards/Pacific Park Brooklyn. This was not part of the two-week Construction Update issued earlier this week. Some of the changes, which will last about eight months, were supposed to have begun in October : 1. One block of Sixth Avenue, between Atlantic Avenue and Pacific Street, will be converted from two-way traffic to one-way northbound only for about eight months. 2. The southeast corner of Atlantic and Sixth Avenues will be closed to pedestrians. 3. At the intersection of Atlantic and Sixth Avenues, both the east crosswalk (which crosses Atlantic Avenue) and the south crosswalk (which crosses Sixth Avenue) will be closed. Those crossing Atlantic Avenue must use the west crosswalk. Those crossing Sixth Avenue must...

Updated: On November 17, a hearing on bonds for 535 Carlton tower; unit count remains the same

According to a notice (below) from the New York City Housing Development Corporation, there will be a hearing next Monday, November 17, on tax-exempt bonds for 535 Carlton Avenue (aka B14), the all-affordable Atlantic Yards/Pacific Park rental tower planned at the corner of Carlton Avenue and Dean Street and the first to be built by Greenland Forest City Partners. The $75 million request will be one of 39 bonding issues to be considered at the hearing, which starts at 11:30 am, in the conference room at NYC HDC office, 110 William Street, 10th Floor, in Manhattan. Public comment is possible, and the hearing  will be webcast  (and can be listened to by phone). The announcement says further information will be available at the hearing or by request before the hearing. I've made such a request and will post an update if/when I get that information. Updated: A bigger building? While I was unable to get additional information from NYC HDC yet, Forest City confirms that the...