From the latest Construction Update: belated announcement of TCOs at 662 Pacific; leasing at 18 Sixth will start in early January
The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, Nov. 29, was circulated 11/23/21 at 12:22 pm (lead time) by Empire State Development (ESD) after preparation by Greenland Forest City Partners.
Also, outside B15, "Permanent sidewalk work continues along Pacific, Sixth & Dean with anticipated completion by the end of December 2021."
Similarly, outside 18 Sixth Ave. (B4, aka Brooklyn Crossing), "Permanent sidewalk work has been initiated along Sixth Avenue."
As interior construction continues, the first TCO is anticipated in the fourth quarter of the year.
Regarding after-hours work at B4 (18 Sixth Ave.), the Construction Update accurately lists weekday work 5 am to 10 pm, and Saturday work 9 am to 5 pm. There are no after-hours variance for Sunday, but work could potentially be from 9 am to 5 pm.
Regarding after-hours work at B15 (662 Pacific St.), the document accurately cites weekday work 6 am to 10 pm, Saturday work 9 am to 5 pm, and Sunday work 9 am to 5 pm.
Regarding after-hours work at B12 & B13, the document accurately states weekday work hours are 6 am to 6 pm. It also says "Saturday work from 9 AM – 5 PM will continue," though no permit for next Saturday has been issued yet.
Tomorrow's permit is from 9 am to 5:30 pm, as were for 11/20/21, 11/13/21, 11/6/21, 10/30/21, 10/23/21, 10/16/21, 10/9/21, and 10/2/21, despite information to the contrary in the Construction Update. A small difference, but not unimportant. And they know better, because I've pointed it out.