Skip to main content

As legal case regarding B15 site finally moves ahead, school opening looks no earlier than 2021

Looking at B15 site from Dean Street. 497 Dean is on right.
A recent judicial decision in the dispute involving the developers of the 27-story B15 (aka 664 Pacific) site, which is slated for market-rate rentals and a school, suggests that the project may finally move forward, though likely at a cost higher than anticipated to developer Greenland Forest City Partners (GFCP).

However, given that pre-construction activities won't start until 2017, at the earliest, and the projected time for pre-construction and construction is four years, that suggests that--unless construction goes faster than expected--the promised middle school won't arrive until 2021, rather than 2018 or 2019, as once projected. The school has been dubbed by backers as M.S. OneBrooklyn.

The background

As described by Supreme Court Justice Sylvia Ash in her 12/5/16 decision (bottom), the developer must demolish an existing structure on site, which will take two weeks, and require excavation to a depth lower than the foundations of the neighboring 497 Dean, a four-story apartment building.

As of June 2016, the "anticipated completion" of the
664 Pacific project was "4th quarter of 2018"
The developer's plan shows a vertical 'secant pile wall' abutting and supporting 497 Dean, supported by diagonal threaded bars known as tie backs. Excavation and foundation construction should take about 12 months. Also, certain portions of 497 Dean's foundation may require waterproofing because it will be exposed.

The developer estimates that construction will take approximately 36 months, so it seeks an order granting entry for 48 months.

The dispute

GFCP says it has offered to work jointly to develop safety plans but 497 Dean refused access. But 497 Dean says that GFCP has not adequately prepared for the excavation and foundation work, and says GFCP has refused to reply to its engineer's report and has withheld crucial details regarding the length and invasiveness of its project.

So 497 Dean asked that GFCP's petition be dismissed or, in the alternative, that it gets a monthly license fee and payment for its engineering and legal fees. GFCP  says 497 Dean was unreasonable, because it barred GFCP from access to conduct a pre-construction survey. And it objects to a temporary license fee.

The resolution

On 6/1/16, the court ordered 497 Dean to allow GFCP to conduct an onsite pre-construction survey. "Based on the papers submitted, this Court is inclined to grant Developer a license" to enter the premises, Ash wrote, given that 497 Dean does not dispute that access is needed or that a four-year period is unreasonable.

Also, GFCP is no longer considering "underpinning" to excavate the foundation of 497 Dean, which the court said could be considered a permanent encroachment.

However, to address the issues raised by 497 Dean, regarding purported inaccurate information, the Court ordered the parties to appear in a conference to address those issues and set forth license parameters. The Court also must determine "what remaining deficiencies, if any, exist with regards to Developer's petition."

Though the decision to award a license fee is discretionary, the judge said, fees are warranted when the license "will entail substantial interference" with the adjacent property for a long period.

However, given that neither party has submitted sufficient information for the judge to assess "what would constitute reasonable licenses fees and/or costs," that issue will be addressed at the conference, which is set for 1/10/17.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…