FCR considers "world's tallest prefab steel structure" for first affordable tower; big savings, but promised union jobs, tax revenues lost, new risks

Updated 8:00 am.

In what seems to be a desperate--or maybe innovative--effort to save money and time, Forest City Ratner may build the world's tallest modular structure to deliver the affordable housing long promised as an Atlantic Yards benefit, the New York Times reports in a front-page story today.

In doing so, however, FCR would establish its own factory to manufacture the components, severely cutting expected on-site union jobs, and presumably cutting deeply into projected tax revenues, thus upending the always optimistic estimates (city, state) of project benefits. (The Independent Budget Office was more critical.)

FCR's Lego-like solution would severely antagonize union construction workers who, fulfilling requests by the developer and their own leadership, fervently and sometimes obnoxiously backed the project at rallies and public hearings. And, as noted by Develop Don't Destroy Brooklyn (below), it would continue a string of broken promises.

Also, in building a 34-story tower at first, FCR would take risks by venturing into a construction technology that is still developing, the current record-holder only rises 25 stories.

FCR's pattern of renegotiation

And the bait-and-switch would continue a pattern of renegotiating contracts in order to save money.

For example, FCR in 2005 bid $100 million in cash for the rights to build on the Metropolitan Transportation Authority's Vanderbilt Yard, only to renegotiate the contract in 2009, paying only $20 million out of the $100 million pledged, with 22 years to pay the rest, at a gentle interest rate.

Similarly, in 2009, FCR renegotiated its business terms with the Empire State Development Corporation, planning to acquire project land through eminent domain in two or more stages, rather than all at once, thus saving on acquisition costs and carrying costs.

DDDB on broken promises

In a press release, Develop Don't Destroy Brooklyn stated:
Jobs, Housing & Hoops! Touted Atlantic Yards “Benefits” Continue to Disappear
Construction Unions Latest Victims of Forest City’s Broken Promises

BROOKLYN, NY—First it was the promised “10,000 permanent jobs.” Then it was the “arena roof garden.” Next it was the “world-class Frank Gehry design.” Then it was the “2,250 units of affordable housing.” Then the “urban room.” And the “eight acres of publicly accessible open space.” Now comes the latest casualty among Forest City Ratner’s endless string of cynical, empty, broken promises – a large chunk of the relentlessly touted construction jobs.

I'd note that the affordable housing and the open space are still supposed to be delivered, albeit on a much longer schedule, and the Urban Room would arrive if and when an office tower, for which there is currently no market, is built.

A scoop for the Times

Charles Bagli of the New York Times, who has paid intermittent attention to the project but is a go-to guy for scoops, has the story, headlined in print as "Atlantic Yards Plans to Build Tallest Prefab," and online as Prefabricated Tower May Rise at Brooklyn’s Atlantic Yards .

(Curiously, the Times's web site last night indicated an alternate headline, with a tougher slant: "In Brooklyn, a Prefabricated Tower May Anger Unions." The Times is accepting comments on the article; here's mine, which focuses on the EB-5 story the newspaper has missed.)

The newspaper reports:
In a bid to cut costs at his star-crossed Atlantic Yards project in Brooklyn, the developer Bruce C. Ratner is pursuing plans to erect the world’s tallest prefabricated steel structure, a 34-story tower that would fulfill his obligation to start building affordable housing at the site.

The prefabricated, or modular, method he would use, which is untested at that height, could cut construction costs in half by saving time and requiring substantially fewer and cheaper workers. And the large number of buildings planned for the $4.9 billion Atlantic Yards — 16 in all, not including the Nets arena now under construction — could also make it economical for the company to run its own modular factory, where walls, ceilings, floors, plumbing and even bathrooms and kitchens could be installed in prefabricated steel-frame boxes.

The 34-story building, with roughly 400 apartments, would comprise more than 900 modules that would be hauled to Atlantic Yards, lifted into place by crane and bolted together at the corner of Flatbush Avenue and Dean Street, next to the arena.
The current record-holder

The tallest modular building in the world, according to a 9/2/09 article in Building Design and Construction, is Victoria Hall, a 25-story apartment tower in Wolverhampton, England. A 9/21/09 article in National Real Estate Investor (source of the photo) calls it 24 stories.

Note the prefab appearance. Does Forest City Ratner's claim that buzzy firm SHoP will design the building apply to the modular units? Or, more likely, would SHoP merely graft a "skin" on the building, as with the Ellerbe Becket arena?

Some flaws

The Times suggests that tall modular buildings require significant bracing, but modular buildings can have their flaws. A 3/26/08 Times article describes a modular building at Yale University that was built in 2004:
“They tried to blend in the appearance of the building with what’s here already,” said Martin Dominguez, a first-year medical student who was also an undergraduate at Yale and has lived in the modular building for 18 months. “They did a reasonably good job, though the building obviously looks pretty modern relative to the other architecture.”

Mr. Dominguez said he was not happy with the quality of the dormitory’s construction — some of the walls do not quite fit together and the floor is uneven in the bathroom, he said.
However, the Times reported, campus housing administrators at another college were impressed with the work and decided to go the modular route.

The benefits of modular

The Modular Building Institute, a trade group, explains that Modular Delivers More than Speed to Completion:
Commercial modular buildings are cutting-edge facilities of the highest quality, efficiency, endurance, and design: cost-effective permanent and temporary buildings that respond to ever-changing demands...

Today, multi-story, multi-unit buildings can be constructed in a factory from steel and concrete. The units, shipped to the site either on a flatbed trailer or on their own axles and tires, are craned into place and joined on site. Once completed, these high-end, factory-built buildings are indistinguishable from site-built construction. There generally are no visual or structural differences whatsoever....

The advantages of modular construction remain the same, however. Commercial modular structures are built in a climate- and quality-controlled environment, where savings of as much as 50% in overall construction time are not uncommon.
Ratner savings, union tensions

The Times reported that Forest City has been designing both a conventional tower and a modular one, and is looking for sites in Long Island City for a factory:
“The company is interested in modular, high-rise construction in an urban setting,” [FCR's] Ms. [Maryanne] Gilmartin said. “It’s driven by cost and efficiencies.”

But it would also infuriate the construction workers who were Mr. Ratner’s most ardent supporters during years of stormy community meetings, where they drowned out neighborhood opponents with chants of, “Jobs, jobs, jobs.”
The Times notes that Forest City promised Atlantic Yards would generate “upwards of 17,000 union construction jobs.” Actually, that's job-years, so 1700 jobs a year over ten years or, more likely, many fewer jobs a year over a much longer period of time, perhaps 25 years.

The Times reports:
Not to worry, Ms. Gilmartin said, “We’re a union shop, and we build union.”

But under current wage scales, union workers earn less in a factory than they do on-site. A carpenter earns $85 an hour in wages and benefits on-site, but only $35 an hour in a factory.
Need for a cost-benefit analysis

Gilmartin should be asked to estimate the actual number of expected jobs, as well as the total in wages. Or the Empire State Development Corporation should do so.

Such numbers should be plugged into the cost-benefit analyses conducted by the city, state, and Independent Budget Office.

Forest City is clearly under pressure to fulfill its obligations and make its expected profits. City officials denied a request for $10 million in additional housing subsidies.

Going to 34 stories?

A firm located in the Brooklyn Navy Yard, Capsys, states that its system is good for 12 stories:
Our system of structural steel framing, concrete floors, and steel-framed walls is ideal for projects as high as 12 stories. Our in-house engineering group is capable of designing modular structures that fit the floor plan of almost any residential building.
Those quoted by the Times say taller buildings are possible, but pose challenges:
“At a smaller scale, prefab buildings have proven to be more efficient, more sustainable and less expensive,” said Thomas Hanrahan, dean of Pratt Institute’s School of Architecture. “The taller the building, the logistical and structural issues become much more complex.”
Keeping the arena block quieter

Unmentioned in the Times: prefab construction would clearly make it easier to build towers around the arena while conducting arena activities.

After all, cranes would be at the site for less time, and fewer workers would be at the site, as well.

Comments

  1. Note the headline on the Times front page right over the Atlantic Yards Story: "A Dearth of Candor."

    Sometimes the Times is vigilant about assessing candor and sometimes it isn't. Sometimes the Times' own lack of candor, having by policy officially relegated Atlantic Yards to the status of a non-story is the important story deserving of a headline.

    ReplyDelete
  2. will all the work be in state workers or out of state workers

    ReplyDelete
  3. Unclear where the workers would come from but if Forest City builds a factory in Long Island City, as has been discussed, that would be in NY.

    ReplyDelete

Post a Comment

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.