Daily News columnist Errol Louis, in a column today headlined Play ball with Bruce, writes:
The biggest myth about the $4 billion, 22-acre Atlantic Yards project in Brooklyn is that it might not get built. So it's long past time for people concerned about the complex to quit fantasizing about how to stop it and start focusing on ways to improve it.
This was made clearer than ever two days ago, when federal Judge Robert Levy hammered another nail into the legal coffin of anti-project advocates by recommending dismissal of Goldstein vs. Pataki, a lawsuit by a handful of holdouts who refuse to sell their property to the project's developer, Bruce Ratner.


Louis calls the litigation "doomed" and likens Atlantic Yards to other projects with public benefits such as Lincoln Center in Manhattan and Melrose Commons in the Bronx, neither of which have, as the Atlantic Yards plan would have, nearly 2000 luxury condos, 2250 market-rate rentals, and 900 (of 2250 "affordable" rentals) at or over market rate.

(In the print edition, there's a big picture of a smiling, benevolent Bruce Ratner.)

Case closed?

Louis calls it a "fool's errand" to go to federal court to impinge on state and local exercise of eminent domain. He notes Levy's citation that federal courts generally stay out of these cases. True, but the question here is whether the Atlantic Yards litigation, based on legal theories developed after the Supreme Court's 2005 Kelo vs. New London decision, will break new legal ground.

Louis predicts that the plaintiffs "will fare even worse in state court, which has long been bent in favor of giving government the power needed to build New York." Again, that's the history--but will this case break new legal ground?

Louis doesn't acknowledge Levy's respectful nod to the substance of the case:
Plaintiffs’ Amended Complaint raises serious and difficult questions regarding the exercise of eminent domain under emerging Supreme Court jurisprudence, many of which were explored in some detail at oral argument. However, in light of my recommendation that this court abstain, it would be inappropriate to address plaintiffs’ claims on the merits.

By the way, Louis also calls the plaintiffs "a handful of holdouts who refuse to sell their property." Actually, a majority are renters (mostly residential, one commercial) who have leases in buildings subject to eminent domain.

Hakeem Jeffries' negotiation

Louis closes by suggesting a model of compromise:
The model of how to do this was laid out by freshman Assemblyman Hakeem Jeffries. After winning election last fall - even before he was sworn in - Jeffries began talking with Ratner and put an entirely new demand on the table: creation of 200 subsidized units that people would own, not rent.

Guess what? Ratner agreed. As a result, hundreds more people will own their own homes, in addition to the thousands who will rent apartments at the site.

All it took was a bit of nerve, sharp negotiating skills and a willingness to face the reality that change in Brooklyn is at hand.


It wasn't exactly an "entirely new demand." The developer had long promised--though it's not memorialized in state documents--the creation of 600 to 1000 "affordable" for-sale units, on or offsite. The announcement in December was for 200 of those units onsite.

We still don't know 1) when those apartments would be built and 2) for what income brackets. I asked Jeffries those questions Wednesday night and he still didn't know.

More affordable housing, or a much slower process?

Indeed, unmentioned by Louis is the gap between Jeffries' current request and the developer's promises. Also unmentioned is the gap between the stated project timeline and the likelihood of far more delay in completing it and producing the affordable housing that supporters so often cite.

Jeffries told me he thought 50 percent of the housing in Phase 1 of the project should be affordable. (Right now, the percentage would be about 25 percent.) That's a significant gap, and meeting that demand would cut significantly into the developer's profits.

Moreover, in December a major project proponent, Kathryn Wylde of the Partnership for New York City, predicted the Atlantic Yards project could take 20 years to build, not ten. And just last week, project landscape architect Laurie Olin said it could take 20 years, requiring him to be contradicted publicly by the guy who hired him, Jim Stuckey of developer Forest City Ratner.

In other words, even as the developer "negotiates," the reality of a delayed development process undermines the developer's promises. When I told Jeffries of Olin's remarks, he seemed dismayed.

Louis's column offers this summary headline: With Ratner's wrecking ball in motion, arena critics must stop stalling and start dealing.

What exactly are they dealing? And with what leverage?

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…