What's coming at the Vanderbilt Yard? More columns needed to support roof, on first block, that will serve as platform for tower construction.
This is the seventh of ten articles on the 6/7/22 meeting of the Atlantic Yards Community Development Corporation. The first concerned the affordable housing timetable. The second assessed an estimated 2031 completion date. The third addressed the impact of a potential Greenland default. The fourth concerned expectations of 421-a benefits. The fifth concerned the deadline for the Urban Room. The sixth addressed timing for the school. The eighth discussed community impacts of construction. The ninth concerned plans for B12/B12 affordable housing. The tenth concerned the Open Meetings Law.
From presentation (at bottom) |
At the meeting, Scott Solish of Greenland USA, which owns nearly all of master developer Greenland Forest City Partners, explained the planned work.
It starts in the area of B5, the building site just east of Sixth Avenue between Atlantic Avenue and Pacific Street, part of Block 1120.
After the columns are installed, then comes a roof on top. That will occur in three sections, including sites for the three towers over the block: B5, B6, and B7.
Director Gib Veconi asked if separate contractors were working on the platform and on B5 or if it's being done by the same firm. (At that time, no contractor had been named, but the contractors for the platform were revealed in another document, as I wrote today.)
"It can be done by the same firm and it can be done by different firms," Solish said, noting that they saw the "platform contract as a single contract done by one firm"--actually two--"and then the vertical buildings can be done by different firms through a segregation of those teams."
What seems to be sticking up in the center is a roof over a street-level ramp at Sixth Avenue. B5, he said would have that "kind of incorporated through the ground floor. So just it's a very tight complex site that's been fully designed and vetted with design professionals and signed off on by the [LIRR] under their own processes.... That driveway in that ramp remain in place and become kind of an enclosed tunnel for the railroad sole purpose of driving vehicles in and out of the yard."
Block 1121, where trains are stored/serviced |
LIRR questions
Director Drew Gabriel asked if the LIRR has 24-hour access.
Comments
Post a Comment