According to the latest Atlantic Yards/Pacific Park Construction Alert (bottom), issued Friday (appropriate lead time) for the two weeks beginning Monday, March 14, overnight deliveries of building sections of an LIRR Employee Building are expected to begin during the week of March 21 via Pacific Street and Vanderbilt Avenue, with building assembly during the day at the Vanderbilt Yard.
Additionally, "Installation of the substation equipment may require overnight, extended weekday work hours, and/or weekend hours to complete." No hours were stated.
While the previous alert noted after-hours sewer connection work will occur along Dean Street near Sixth Avenue for the B3 (38 Sixth Avenue) site at the southeast corner of the arena block, the new alert states that sewer connection work, which began March 8, will be done normal work day hours and is expected to take 2 weeks. It may require temporary closures of portions of the sidewalk for safety reasons.
Saturday work may continue at B2 (461 Dean Street), B3, and B14 (535 Carlton). There could be weeknight work at B14 until 9 pm. Also, there will be weekend work in the Long Island Rail Road tunnel and rail yard. Hours were not reported.
Other new work is reported verbatim below.
B3 - 38 Sixth Avenue
• Superstructure phase of construction will continue with the framing and pouring of the 2nd floor.
Block 1120 & 1128 Demolition
• A two-story garage remains on site and is expected to be demolished.
How to Reach Pacific Park Brooklyn Community Liaison Office (CLO)
The Community Liaison Office is located at Atlantic Center Mall, 625 Atlantic Avenue on the 3rd floor. Visitors seeking the office should enter through the mall entrance located at the corner of Atlantic Avenue and So. Portland Avenue. The CLO’s hours are M-F from 9am – 4pm and can be reached by phone at 866-923-5315 and by email at communityliaison@pacificparkbrooklyn.com
Additionally, "Installation of the substation equipment may require overnight, extended weekday work hours, and/or weekend hours to complete." No hours were stated.
While the previous alert noted after-hours sewer connection work will occur along Dean Street near Sixth Avenue for the B3 (38 Sixth Avenue) site at the southeast corner of the arena block, the new alert states that sewer connection work, which began March 8, will be done normal work day hours and is expected to take 2 weeks. It may require temporary closures of portions of the sidewalk for safety reasons.
Saturday work may continue at B2 (461 Dean Street), B3, and B14 (535 Carlton). There could be weeknight work at B14 until 9 pm. Also, there will be weekend work in the Long Island Rail Road tunnel and rail yard. Hours were not reported.
Other new work is reported verbatim below.
B3 - 38 Sixth Avenue
• Superstructure phase of construction will continue with the framing and pouring of the 2nd floor.
Block 1120 & 1128 Demolition
• A two-story garage remains on site and is expected to be demolished.
How to Reach Pacific Park Brooklyn Community Liaison Office (CLO)
The Community Liaison Office is located at Atlantic Center Mall, 625 Atlantic Avenue on the 3rd floor. Visitors seeking the office should enter through the mall entrance located at the corner of Atlantic Avenue and So. Portland Avenue. The CLO’s hours are M-F from 9am – 4pm and can be reached by phone at 866-923-5315 and by email at communityliaison@pacificparkbrooklyn.com