Skip to main content

From the latest Construction Update: large boom lift being used inside Barclays Center, then moved periodically across the street; tree guards for three trees on Dean Street

For the second straight time, the two-week Atlantic Yards/Pacific Park Construction Update has been released on the Friday before the official Monday date, in this case June 8.

On the one hand, that is welcome--frankly, it should have been the pattern all along, as opposed to distribution on the day it was dated, or a day or two after.

On the other hand, even the early delivery is being used to obscure changes that should have been disclosed earlier. For example, the document distributed yesterday, June 5, contains this passage:
Miscellaneous Work
*During this period it is expected that from June 4 until June 16, work will be done inside the arena which requires use of a 150ft boom lift; this equipment will be removed from the arena when the arena is in use and will be stored as needed in broadcast lot. The work hours will be 4PM-7AM.
As I tweeted yesterday, that left a lot out:
And what, pray tell, is this "miscellaneous work"? Interior roof work?
How complicated and complicating will it be to move it to the broadcast lot *across the street*?
And if this started yesterday, why wasn't this disclosed in the *previous* construction update?
Also, as I wrote yesterday, the state and developer Greenland Forest City Partners belatedly disclosed that Sixth Avenue between Atlantic Avenue and Pacific Street would be closed for an extended period of time.

Some trees protected

The severe narrowing of Dean Street and Carlton Avenue bordering the southeast block of the site has led to damage to several trees, and officials are finally taking steps to improve the situation. The latest alert discloses:
Three-sided tree guards for three trees located on the opposite side of Dean Street across the street from the [B11] site [near Vanderbilt Avenue] will be installed.
New work at B2?

And despite improvements, notably the use of a red typeface and asterisks to purportedly indicate new work being reported, not everything indicated in red and with an asterisk actually is new. Whatever sloppiness or deceptiveness, it disserves the readers.

For example, the latest alert states, regarding the B2 modular tower at Flatbush Avenue and Dean Street:
*Work related to the erection of modules for floors 11, 12, and 13 is continuing during this reporting period.
* Limited interior work will begin on modules that have already been installed. 
Actually, that was announced in the previous alert.

New work at B3

There will be new work at the B3 tower site at Dean Street and Sixth Avenue:
*The approved MPT plan will be installed during this reporting period. This includes the installation of the site fence and gates as well as removal of street lights inside of the B3 MPT.
*Excavation and foundation activities will begin during this reporting period. Work includes drilling of soldier beams for the SOE system, soil excavation and the installation of lagging. Protocols for the trucks entering and exiting the site have been put in place, providing instruction on roadway routing to and from the project site, queuing of trucks while on site and vehicle idling restrictions.
*The removal of the stationary bollards and retractable bollards will take place during this reporting period.
Work at Railyard,- Block 1120 & 1121
*During this reporting period, the Contractor will continue excavation and hauling of soil from Blocks 1120 and 1121. Soil that has been classified as clean, contaminated or hazardous will be removed from the site as part of the excavation activities and brought to appropriate disposal locations. Protocols for the trucks entering and exiting the site have been put in place, providing instruction on roadway routing to and from the project site, queuing of trucks while on site and vehicle idling restrictions.
Support of Excavation (SOE) work including the installation of lagging and tiebacks will continue within this area during this reporting period.
Manhole and duct bank installations will be ongoing in Blocks 1120 and 1121 during this reporting period.
*Foundation footing and pier rebar, formwork, and concrete installations will be ongoing in Blocks 1120 and 1121 throughout this reporting period.
*Pacific Street Retaining wall rebar, formwork, and concrete installations will be ongoing in Block 1120 and 1121 throughout this reporting period.
*Caisson pile installation for load test(s) is scheduled in Block 1120 during this reporting period.
Demolition of Atlantic Avenue retaining wall in Block 1120 will continue during this reporting period. 
LIRR Yard Activities – Atlantic Avenue

This is indicated to be new, but, other than the bolded, is not:
*Excavation and hauling of soil will be ongoing during this reporting period.
*Support of Excavation (SOE) work including the installation of lagging and tiebacks will continue within this area during reporting period.
*Temporary utility relocation work at the west portal will be ongoing during this reporting period.
LIRR Yard Activities – Night/Weekend Work
Tunnel WorkWeekend Electrical Utility work (conduit and support installation) is being performed inside the LIRR Tunnel and will continue during this reporting period. Crews will access the Tunnel via the LIRR Yard entrance on Atlantic Avenue. This work is currently scheduled to continue through the end of 2015.
Atlantic Avenue and 6th Avenue Intersection*Friday June 5th through 5 AM Wednesday, June 10th
o The Atlantic Avenue and 6th Avenue intersection temporary decking will be completed
during this reporting period.
o 6th Avenue will be closed from Pacific Street to Atlantic Avenue (6th Ave Bridge) and there will be varying lane closures on Atlantic Avenue throughout the weekend to allow for temporary repaving of the Atlantic Ave and 6th Ave intersection.
o Work will include milling, grading, and paving of the intersection to complete installation of the temporary decking. This temporary decking will allow 6th Avenue to remain open while West Portal construction continues at the 6th Ave and Atlantic Ave intersection.
o There will be no pedestrian access on 6th Avenue between Pacific and the north side of Atlantic Avenue during the period referenced above.
o Flagmen and/or TEAs will be posted at the intersections to help direct traffic and pedestrians.
o Work will occur 24 hours a day during the period referenced above. A community notice was distributed on June 5, 2015 and On-Site Environmental Monitor (OEM) will be overseeing these activities. Portable fences with noise blankets will be used across the entire length of the fence
Block 1129, B11 – 550 Vanderbilt Avenue
*Installation of building foundations and installation of underground plumbing and electric materials will be completed during this period.
Backfilling on the West foundation wall utilizing stockpiled material is ongoing
Mobilization of the field office complex will continue during this reporting period.
*Three-sided tree guards for three trees located on the opposite side of Dean Street across the street from the site will be installed.
*Con Ed is scheduled to commence bringing additional electric power into a property manhole located within the site on Dean Street.
Block 1129, B14- 535 Carlton Avenue
*Excavation and foundation activities will continue during this reporting period. Work includes drilling of tie backs for the SOE system, soil excavation and the continued installation of lagging to the same elevation. Soil that has been classified as clean, contaminated or hazardous will be removed from the site as part of the excavation activities and brought to appropriate disposal locations. Protocols for the trucks entering and exiting the site have been put in place. These protocols provide instruction on roadway routing to and from the project site, queuing of trucks while on site and vehicle idling restrictions. [The first sentence is not new, but the rest of the paragraph is new]
A tie-back drill rig will be working, drilling the second and third level of tie backs for the SOE system. Drilling commenced in the northwest corner of the site at Pacific Street and Carlton Avenue and is working its way counterclockwise around the site.
Installation of spread footings and slab on grade is ongoing. A small crane will be used inside of the excavation to assist in concrete operations.
Installation of foundation waterproofing and pouring of foundation walls is ongoing.
Site mobilization will continue consisting of electrical work to power contractor field office and relocation of light poles to outside of site fence.
Atlantic Yards/Pacific Park Brooklyn Construction Alert June 8 2015

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.