Skip to main content

Cranes around Barclays Center (including for unplanned green roof) linger; potential tension between arena operations and larger project

I'm leading a walking tour Sunday of Atlantic Yards/Pacific Park/Barclays Center/Prospect Heights (via Municipal Art Society), and present several posts in preparation. One thing to remember: the project remains very much in process. Some impacts feared, expected, or welcomed have not emerged because they were calculated on a larger/full buildout. Others were never anticipated. 

(Updated with comment at bottom)
The B2 crane; the B3 crane is in background

One lesson from Atlantic Yards, as I've said, is that it's a "never say never" project. For example, today, the arena is ringed with three cranes, and they're lingering longer than projected.

No one expected cranes on the arena block for long, because four towers were supposed to be built along with the arena.

That didn't happen. The arena was shrunken to save money, decoupled from the towers to allow a slower buildout, and constructed first.

Beyond that, no one expected the crane for B2, the modular tower at the intersection of Dean Street and Flatbush Avenue, to linger so long.

It arrived in August 2013 and was supposed to be gone by the end of 2014, when the building was supposed to be done. Instead, it's still here, through the third quarter of 2016, when the troubled, delayed building is now expected to be finished.

And no one expected two--and ultimately three--cranes to be used to install a green roof on the Barclays Center because, well, there was no plan for that green roof. (There was an earlier plan for green roof to be built with the arena. That was scrapped, and this one's not the same.)

The new green roof construction--a new exoskeleton--was driven by the desire to make the roof look more attractive to potential residents in adjacent towers and the need to tamp down bass escaping during certain concerts.

The cranes come late, so the roof is late

From Atlantic Yards Watch's AY Cam
So now there are three cranes around the Barclays Center, and there may be four.

The B2 crane, as noted above, arrived in August 2013.

The green roof crane on Atlantic Avenue, which blocks traffic, arrived in October 2014. So did the crane placed on the site for the B3 tower at the corner of Dean Street and Sixth Avenue. (This doesn't block traffic.)

Actually, both were due in August, as the chart below indicates. So they're behind.

As I wrote in February, the green roof is several months behind schedule, not that representatives of the arena developer have fully explained.  (Yes, it has been a cold winter, but they got a late start. Was it to keep the site clear for the DNC visitors?)

Note that, according to the project timeline released last June, all cranes were supposed to be gone by the end of January, with the Flatbush Avenue crane placed only that month.



Instead, as disclosed in February at the periodic Atlantic Yards Quality of Life meeting, Forest City Ratner external affairs executive Ashley Cotton said  structural work on the arena should be completed in May, Cotton said, after a crane is placed on Flatbush Avenue, "probably towards the end of April."

That's about five months late, though faster work at the final end of installation may make the overall project only two months late.

Note that the Flatbush crane will necessitate the closing of a lane of traffic and likely additional traffic congestion. It was not originally supposed to be erected while the Atlantic Avenue crane was still up. Now that seems likely.

And the Atlantic Avenue crane has already snagged traffic, as even Empire State Development CEO Kenneth Adams observed.

The installation of sedum--the plants serving as green roof materials, as with the top of the subway entrance on the arena plaza-- will be done in September, Cotton said.

If so, that means they'd be catching up on a good part of the delay, since the sedum was supposed to be installed by July, two months before September.

The view from Dean Street and Sixth Avenue, looking northwest
Inevitable tensions?

There surely are tensions between those operating the arena--who presumably would prefer no cranes or construction interrupting the path of eventgoers--and those building the towers and infrastructure around the arena.

Looking east along Atlantic Avenue
Then again, those tensions should be ameliorated by the fact that those two parties share ownership: Forest City, which is building B2 on its own and everything else in partnership with the Greenland Group, owns 55% of the arena operating company.

But the arena is for sale.

If Forest City sells its share of the arena (likely along with its 20% share of the Brooklyn Nets), its focus--and that of Greenland--will be getting the residential buildings done, plus infrastructure.

If that interferes with arena operations, I suspect plowing forward will take precedence. If so, that means the new operators of the arena might feel frustration at the unfinished situation around them.

On the other hand, they should know what they're getting into.

The long view

And in a few years, most likely, the cranes--not just for the roof but also tower construction--will be gone.

By then, when the towers are finished, most people won't remember the cranes. They'll be looking at an arena block that looks *something like* the below image, which clearly diminishes the actual scale (see above to see how much the arena looms from a pedestrian's view).

Then again, if and when they build B1, that would expunge the arena plaza and open up another can of worms.

Update: a comment from resident Peter Krashes:

I would add that it is not just construction that produces a potential tension between the arena and a developer of residential buildings in the area. Arena operations -- when they spill out on public sidewalks and streets -- are also a potential source of tension. After all, the developer has to market homes, and not every potential tenant or property owner will embrace the sidewalk or street outside their home being co-opted by a private, for profit entity on a regular basis.
This is not just an issue for those events for which the City permits street or sidewalk closures. In some cases pre and post event, it is difficult to walk in the opposite direction from crowds associated with the arena. This is because the sidewalk widths on the arena block were not designed with the idea that crowds would arrive or leave in a short time frame.


Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.