Skip to main content

Featured Post

Atlantic Yards/Pacific Park infographics: what's built/what's coming/what's missing, who's responsible, + project FAQ/timeline (pinned post)

Today, contractor begins work on water main on south side of Atlantic Avenue east of Sixth

Yesterday, Empire State Development issued a Supplemental Report to the previously issued two week look– ahead regarding upcoming construction activities at Atlantic Yards/Pacific Park
LIRR Yard Activities – Atlantic Avenue
New Information:
On October 31, 2014 the contractor will commence work related to the cutting and capping of a 36” New York City Department of Environmental Protection (NYCDEP) trunk water main located on the south side of Atlantic Avenue. Much of this work, which entails excavation utilizing an excavator and dump truck, will take place inside the Atlantic Avenue MPT area located to the east of 6th Avenue. This work will not affect water service in the area. Work overall duration will be 1- 2 weeks, with at least one week happening during this reporting period. It is expected that this work will be performed during day time work hours.

Comments