Skip to main content

Barclays Center opened with defective bolts, not disclosed fully to Department of Buildings; problem hints at why ESD, construction monitor have obscured the issue

The New York Times's scoop today, Problem With Weak Bolts Has Complicated the Barclays Center’s Early Days, reveals that the arena opened even as the developer acknowledged that more than 1700 defective, weak bolts had been used to attach the facade.

The article suggests that the city Department of Buildings (DOB) was not sufficiently informed by developer Forest City Ratner about the bolts, which were half as strong as requested.

Bucket of apparent replacement bolts, Sept. 2012,
photographed outside ASI Limited office on Dean St.
Moreover, unmentioned in the article, neither Empire State Development, the state agency overseeing the arena, nor the construction monitor for bondholders have been fully forthcoming about this issue.

In fact, both have interrupted their regular schedule of reports, for reasons unexplained. The new information could bolster suspicion that the reports were withheld to obscure the problem.

Indeed, the reports that did emerge obscured the problem in their own way, failing in one case to indicate defects and in the other the scope of the defects. It's still unclear how much danger the defective bolts have posed.

The scoop

The Times's Charles Bagli writes:
And lately, iron workers have replaced hundreds of bolts that anchor the panels to the building’s structure. Engineers determined that weaker ones were originally installed, raising concerns about the structure’s integrity.
The incorrect bolts were discovered only a month before the Barclays Center was scheduled to open on Sept. 28. ...
After examining every joint, engineers determined that only 8 percent of the 23,351 weaker bolts needed to be replaced.
Who was told

The DOB says it was not informed:
“The department was not made aware of this issue,” said Anthony Sclafani, a Buildings Department spokesman. “We would expect to be notified in a case like this.”
But Forest City provided a copy of a nine-page letter concerning the bolts that it said had been filed with the Buildings Department on Sept. 14. That was the day the agency issued a temporary certificate of occupancy [TCO] that allowed the arena to open as scheduled.
The letter, from an engineering company, outlined a plan to address the “recent discovery” that incorrect bolts had been used. It did not indicate how many bolts would be replaced, only that a “change out” had begun.
In other words, whatever the DOB was told, it wasn't enough. (The DOB web site indicates multiple outstanding requirements for the current TCO, but I was unable to get any details when I inquired.)

What ESD told the public

The problem was hardly explained to the public by ESD, which issues regular two-week Construction Updates prepared by Forest City Ratner.

While the work has apparently continued since the arena opened--the Times reports that workers last month "were replacing the final batch"--ESD stopped issuing regular updates after mid-October, as the graphic above indicates.

Moreover, the Construction Updates issued 9/24/12 and 10/8/12 did not indicate the scope of the problem, stating merely that facade panels would continue to be installed and replaced. There was no mention of defective bolts.

The 12/3/12 Construction Update made no mention of facade panel installation.

What bondholders were told

Merritt & Harris, the construction monitor that reports to the state, Forest City, and bondholders, also has been obfuscatory.

While the Times reports that an engineering firm discovered the that the "fabricator had sent five-eighths-of-an-inch bolts that were half as strong as those of that size that had been ordered," such detail has not appeared in the Merritt & Harris reports.

First, as I wrote 12/7/12, Merritt & Harris apparently skipped public issuances of two Site Observation Reports, failing to make public #30 and #31.

Second, the information shared in Merritt & Harris's 11/30/12 document contained the exact same text regarding Deficiency Items as in the 4/2/12 document, except that the later document references a later consultant's report.

In other words, while the problem apparently persisted, there was no indication of the extent--except for a failure to reference an expected "sign off of all corrective work" expected "to be made available by the first week of October 2012."

The Merritt & Harris documents, while indicating "defective installation," did not specify defective bolts nor indicate their extent.

From the April Merritt & Harris report

From the November Merritt & Harris report



Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.