Report: schedule indicates Carlton Avenue Bridge delayed, but could meet arena opening date thanks to overtime; ESDC says "mitigation plan" reference incorrect; arena still on schedule for September 5; transit connection slips to mid-August

The Carlton Avenue Bridge is still scheduled to be completed on 10/3/12, five days after the first event at the Barclays Center, but, according to a report from the construction monitor for the arena bond trustee, Forest City Ratner is paying overtime to meet the completion date, and also has asked the city Department of Transportation for the OK to open the bridge with temporary street lighting and railing.

The report, dated 6/4/12 and based on a site visit 4/26/12 and a later document review, was issued by Merritt & Harris, which reports to the bond trustee, developer Forest City Ratner, and the Empire State Development Corporation.

The report also states, "Nevertheless, the Empire State Development (ESD) has requested that FCRC propose a mitigation plan to control and alleviate the traffic flow congestion for the first event at the arena, scheduled for September 28, 2012."

Is that so? Arana Hankin, Director, Atlantic Yards Project, ESD, told me the report was wrong. Merritt & Harris, she suggested, might be referring to the Transportation Demand Management plan (TDM) developed by Forest City.

Then again, the TDM plan refers to arena activities in general, not "the first event at the arena."

I queried Forest City Ratner spokesman Joe DePlasco, who also did not confirm the Merritt & Harris account. "As the report indicates we remain confident that we can meet the opening date and are looking at some temporary measures too to ensure that the bridge is operational when the arena opens," he stated. "We will be developing event specific traffic and transportation plans for every event."

Forest City is contractually obligated to ensure that the bridge is open before the arena opens, but the penalty is rather toothless: freezing of the developer's rights to move forward on any new residential development--which is already delayed.

Arena schedule

The report, after finally analyzing an ultimately not-so-mysterious GMP2 [Guaranteed Maximum Price], indicates that the arena remains on schedule for a substantial completion of 9/5/12, providing some 23 days to test the building before it opens.

The final completion date remains 6/30/13.

Transit Connection

The adjacent Transit Connection, once supposed to be finished by 4/2/12, is now scheduled for 7/14/12--though the monitor suggests that "a mid-August completion date is more realistic."

Given that the Transit Connection will open in conjunction with the Arena--why not open it somewhat earlier--the report says the slippage "will have no impact on the overall project schedule."

The reason for slippage is said to be "early delays," but, as I've written, the early delays were overcome.

Number of workers down

According to the report, there were 490 people working on the arena and 48 working on the Transit Connection, a decrease attributed to the "substantial completion of the steel work."

That's a decrease from the previous report, which counted 520 and 62 workers respectively, and likely the one before that. Note that Merritt & Harris does not count workers at the separate railyard project.

Reserves exceeded

Given additional costs, including for interior finishes, equipment upgrades, the building facade, and facade lighting, costs have increased, drawing down existing contingency reserves, requiring Forest City Ratner to put up another $30 million.

Deficiencies with exterior steel being fixed

Several deficiencies in the exterior were identified in the report two months ago, and are being remedied.

Schedule: arena

The schedule is based on comparing the amount of money spent to the amount projected. It appears that the arena is ahead of schedule, but that required extending the schedule so that projections would be spread over a longer time period.


Schedule: transit connection

The transit connection schedule has also been tweaked. For example, an earlier version of this chart indicated that, by August 2011, actual spending began to hit parity with projected spending, and then dip.

More photos: courtside club, new curbing

The report also includes photos, as indicated below, of work in progress.


Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.