Skip to main content

From the latest Construction Alert: new rail track, progress on Carlton Avenue Bridge, delay in traffic mitigation work, creation of surface parking lot to start May 1 (though no plans announced)

Below are some excerpts from the latest two-week Atlantic Yards Construction Alert, dated 3/26/12 (and embedded below), and released yesterday by Empire State Development after preparation by Forest City Ratner.

The highlights include:
  • installation of new rail road track in the west end of Block 1120
  • progress on the North Abutment of the Carlton Avenue Bridge
  • removal of an access ramp to the arena
  • work on the remaining traffic mitigation work will begin in late April, not merely April
  • work on the surface parking lot should begin May 1, though no plans have been announced
  • streets lights and curbs are being installed on Flatbush Avenue
Below, I've bolded the notable changes from the previous alert.

Arena Site/Deliveries & Site Access
• Hunt has demobilized the access ramp at Dean Street and Flatbush Avenue. The main gate and delivery ramp is now and will remain for the future at Pacific Street and 6th Avenue. The access route to the Pacific gate remains posted at the site and is the same as it has been throughout the project. Access is also available via the Atlantic Avenue gates at the Fort Greene intersection, midway between the Ft. Greene and 6th Avenue intersection and limited access for concrete trucks on Flatbush Avenue across from 5th Avenue and at the Dean Street intersection. The removal of the Pacific Street [sic; probably Dean Street] ramp, from the bottom to the top, is projected to begin during this reporting period. The removal is anticipated to occur over several reporting periods.
Revisions to the perimeter construction fence are projected to begin this reporting period, in order to allow the site construction activity to ramp up. Adjustments will be made to the portion of the fence along Dean Street & 6th Avenue and Dean Street & Flatbush Avenue. Changes will not be made until permit approval has been secured.
Steel erection and stadia installation
Primary (truss) roof steel erection has been completed. Secondary roof framing will be completed during this reporting period. Preparation to erect the main entry canopy steel is expected to begin this reporting period. The erection of the canopy steel framing will start during this reporting period.
Façade Installation
• The installation of curtain wall and curtain wall/lattice panels will continue on the Flatbush Avenue elevation as needed, and then following the canopy steel erection. In the interest of public safety, and as approved by the New York City Building Department, pedestrians using the east side sidewalk of Flatbush Avenue next to the arena may be temporarily diverted to across the street by Hunt flagmen during high level work. The façade erector will continue with installation of panels along the 6th Avenue elevation this reporting period, and turn the corner west on to the Dean Street elevation, installing the high panels. Installation of the erection clips will continue on the Dean Street elevation during this reporting period.
• The façade subcontractor will continue to work a second shift as needed throughout this reporting period. Work may be performed on the 6th Avenue, Flatbush Avenue and Dean Street elevations on second shift.
Waterproofing & Fireproofing
• The waterproofing of the interior walls of the east stormwater retention tank has been completed. The application of interior waterproofing at the west stormwater tank has been completed.
• The exterior tank roof waterproofing for the west tank will start this reporting period.
• The maintenance of temporary weather walls (visqueen & tarps) as well as temporary rubber roofing, to provide protection through the spring months, will continue this reporting period.
Mechanical, Electrical, & Plumbing
• Permanent power from ConEd is projected to be completed on the service side this reporting period.The transformers have been placed in the ConEd vault. The first of the transformers has power to the line, or service side, and permanent power should be available to all transformers on or about March 19th to the 26th.
Interior Build-out
The installation of applied finishes will continue during this reporting period at the Event Level restrooms and showers in the Nets Campus areas, kitchens and food service areas, as well as the Main Concourse restrooms and concessions, and the Lower/Upper Suite restrooms, concessions and suites.The delivery of the primary kitchen and concessions equipment will continue during this reporting period.
New Subway Entrance--Concrete
• The sub-passageway floors have now been placed.
New Subway Entrance--Transit Canopy
• The steel and concrete roof for the canopy is now complete along with the spray fireproofing. The contour slab has been completed. Roofing work will commence during the month of April.
Tile work is underway. The steel stair nosings and stair tile work at the main entrance stair will follow the completion of the MEP work, painting and canopy ceiling installation. MEP work will progress over the next 2 months and will be followed by the canopy ceiling. Ductwork installation has commenced and electrical work will follow.
Elevator/Escalator
• The two new escalator trusses from the fare array area to the new plaza have been set and final assembly continues. Electrical and fire protection work at the escalator trusses is now complete. The new elevator enclosure has also been erected and elevator installation continues. Work activities have been resequenced to accommodate canopy work items. Elevator cab installation has commenced. Stainless steel work for the escalator is in progress.
Rail yard/Drainage System
• Posillico/Tully is working from west to east to install deep drainage piping in the yard. They will also continue excavation for the associated stormwater manholes. This work will be ongoing for the next month. Through this period, Retention Basins “A”, “B” and “D” have been completed and back-filled. Work has moved to the final basin, Basin “C”.
Electrical Ducts and Manholes
• Conduit formwork continues to be placed throughout the yard for underground electrical duct banks (for both train traction power and signal). Precast manholes continue to be placed at multiple locations. This work will continue through the next month.
Track Work
• Installation of rail road track has begun in the west end of BL1120, to include welding of running rails. Track work will continue, working typically from west to east, until the yard is completed.
• Stone ballast has been, and will continue to be intermittently delivered during the night shift.
[Previously: the track work was to continue "through the next 3 month period." Now it's ambiguous.]

Carlton Avenue Bridge
• Construction of Pier #2 is nearly completed. Forming and pouring of the pedestals at the top of the stem wall will take place in this reporting period. The footing for the North Abutment will be poured during this reporting period. Currently, forms and reinforcing are being placed.
East End (former Gasoline Station)
• Construction of a tall retaining wall along the Vanderbilt Ave. end of the yard is set to begin once permits have been secured. Work will require that e west southbound traffic lane and adjoining sidewalk be taken out of service when concrete trucks are present from which will be pumped concrete into the wall below. Work has begun within the yard on pouring the concrete footing for this wall.
Replacement of Adjacent Water Mains and other Utility Work
• On behalf of the DEP, FCRC is managing the installation of a new water trunk main and associated distribution mains on Flatbush and Atlantic Avenues. The work is divided into three stages.
o Stage One is the work on the west side of Flatbush, north of the Atlantic intersection, continuing across Flatbush to the edge of the transit improvements on the arena block...
o Stage Two is the work along the south side of Atlantic Ave. from a location just west of the former 5th Avenue bed, running eastward to a location west of the 6th Avenue intersection.
o Stage Three is the area between Stages One and Two, across Flatbush Avenue and the top of the future new transit station improvements.
...• Stage Three, which is over a portion of the transit area, was completed in March.• Catch basins at the corner of Pacific and 6th Avenue will be modified during April. Work will begin during the next two week period pending receipt of DEP approval.
Block 1129 (Carlton, Dean, Vanderbilt, Pacific) – Construction Staging
Contractor work related to digging test pits for soil sample classification took place from March 12 through March 14th. There is no other work currently on-going or scheduled to prior the construction start date of May 1, 2012 for surface parking lot.
Traffic Mitigation Site Work Atlantic Avenue Medians
Work is expected to begin in late April 2012 on the remaining traffic mitigation work, most of which is made up of raised medians along Atlantic Avenue from Flatbush Avenue to Vanderbilt Avenue. OCMC is reviewing the scope and location of the medians and will determine whether the work shall be performed during limited daytime, which will prolong the construction period, or at night between 10 pm and 6 am. If the work is done at night, mobile light units will be used to illuminate the work area. The arena block, Carlton Avenue Bridge reconstruction and DDC utility work between Carlton and Vanderbilt Avenues also take lanes out of service. Therefore, the median work must be scheduled block by block to coordinate with the other work schedules and MPT configurations. Because the work is a few feet directly above the LIRR tunnel into Atlantic Terminal, the means and methods must be reviewed and approved by the LIRR.
Arena Site Work
The curb installation work and street light installation work will now commence on Flatbush Avenue during the hours of 10 PM to 6 AM. This work will continue for the month of April. Upon completion of this work, the sidewalks in front of the arena will then be installed. The work will continue in May.
Maintenance & Protection of Traffic (MPTs)
• The MPT on 6th Avenue, from Pacific Street to Dean Street and on Dean Street from 6th Avenue to Flatbush Avenue will be relocated from the property line to the curb line to facilitate the installation of the bollards during this reporting period.
NYC Transit Improvements:
Work related to the BMT structure and below grade concrete, steel and MEP work may be conducted on Saturdays, March 31st and April 7th during this reporting period.
Arena Site Work
Work along Flatbush Avenue as described above will occur during this reporting period during weeknight evening hours as described above under approved DOT stipulations.
AY Construction Alert 3-26-2012

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…