Deconstructing a dubious, uninformed WNYC Atlantic Yards round-up

When I saw the headline on an WNYC article today, Atlantic Yards Construction Tests Patience of Residents, I thought that maybe they'd drawn from the ongoing Atlantic Yards Watch articles and incident reports on the impact of construction, such as the recent Trucks at Atlantic Yards continue to violate site protocols, obstructing a public street.

Nah.

The article is a remarkably uninformed, "View from Nowhere" hodgepodge. It's annotated below.

The opening

Construction continues on the developer Forest City Ratner's Atlantic Yards project in Brooklyn. Disruption is worse at night, especially for Prospect Heights residents. That’s when work crews spill onto Flatbush Avenue and snarl traffic. The work is testing some residents' patience.

Christine McCoy lives nearby and shops at was the Pathmark supermarket located across the street from Atlantic Yards, which will include Barclays Arena, the new home for the Nets NBA basketball team. “The traffic is crazy. I'm not going to be coming to this Pathmark anymore, because it is not going to make any more sense,” McCoy said.


Actually, the issue is less the crazy traffic by day but the impact of construction on adjacent blocks, as documented by Atlantic Yards Watch.

The modular issue

Forest City Ratner's project has been mired in controversy since construction began in the fall of 2009. The $5 billion project has faced numerous lawsuits and has struggled to get financial backing. The developer recently revealed that one of the residential towers on the site, a 32-story high-rise, will be constructed from pre-fabricated modules. Opponents have complained that the modules will result in fewer jobs for local construction workers.

Yes, opponents (i.e., Council Member Letitia James) have launched such complaints, but, as with a New York Times round-up article last July, the press shouldn't have to find "opponents" to complain.

The press should, as a guardian of the public interest, compare Atlantic Yards promises to the current porjections.

The lawsuit

The most recent lawsuit against the Atlantic Yards Development Company and Forest City Ratner companies was filed in Federal Court in Brooklyn on November 15. The complaint was filed by seven former apprentices hired to work at Atlantic Yards. They alleged that they were employed for only two months and they didn’t get to work on Barclays Arena or Atlantic Yards. Additionally, the plaintiffs alleged they received no “wages or other compensation” for their work. A court date has been set for February.

No, they weren't hired to work at Atlantic Yards. They were accepted into a training program (as part of the Community Benefits Agreement) and (according to the lawsuit) promised jobs at the project and union cards.

The "other side"

Despite these issues, there are many neighborhood residents who are eager for the project to move forward.

Jacob Parris owns Vinnies, a men's boutique a few blocks away from Atlantic Yards. Parris believes the arena will improve foot traffic to his store. “Right now everybody's driving...you know, they're driving either, past, going into the city, or driving back to Brooklyn,” said Parris. “But now with the stadium there, it'll be something to look, at something to want to walk through,” he said.


Vinnies is next to a couple of dense neighborhoods, so there's a lot of foot traffic on Flatbush Avenue. It's fair to say that retail serving nearby residents is doing fine--as long as they have a long-term lease--but more regional retail, such as Vinnie's, should do better with arena crowds.

Oh, and the Barclays Center featured Vinnies in a spotlight promotional video. Keep that in mind when you hear positive statements about the arena from Junior's, Hooti Couture, BK Terrace, Bergen Comics, all featured in such videos.

The irrelevant mention

Other fans of the project include some skateboarders who live in the neighborhood. James Matthews, 13, Germain Gilmore, 12, and Malakai Sankar, 13, said the new arena will be cool. “I think that they should let us kids get in for free,” Matthews said.

This was put in because... maybe it sounded good on audio? Otherwise, it's irrelevant.

The close

The project includes more than 6,000rental units, more than a third of them will be for low income and moderate income families. The company said it will break ground on the residential tower early next year. It's expected to take 18 months to complete. The basketball arena is expected to open next fall.


Actually, of the 6430 planned (not included) housing units, 1930 would be condos. Of the 4500 rentals, half would be subsidies.

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…