Real public works (transportation), the mis-described "wave of development" (as of 2007), and Atlantic Yards

At the panel Roads to Nowhere: Public Works in a Time of Crisis, last night at the Museum of the City of New York, the discussion focused on the Access to the Region's Core (ARC) train tunnel between New Jersey and New York vetoed by New Jersey Governor Chris Christie, the Second Avenue Subway, and relatively smaller fixes like Bus Rapid Transit.

All of those are infrastructure projects that drive development. None are mega-projects like Atlantic Yards, run by a single private developer. (Atlantic Yards would add a transit entrance to an existing station, thus mainly serving the arena, and an upgraded but smaller railyard, not previously requested by the Metropolitan Transportation Authority.)

Why did Christie act? Jeff Zupan of the Regional Plan Association suggested it was a matter of politics, as he had inherited a project approved by his predecessor: "politicians are always thinking about cutting a ribbon in their terms in office."

Joan Byron of the Pratt Center for Community Development added that Christie was elected by South Jersey drivers, not North Jersey transit riders. She argued that transit advocates had done too little to build a base of public support. (Also see Benjamin Kabak's good summary on Second Avenue Sagas.)

That "wave of development"


I couldn't help but think back on a misguided 1/1/07 New York Times overview, headlined Wave of Development, Cleared for Takeoff:
City, state and federal agencies granted final approvals last month to a half-dozen wide-ranging projects in a political aligning of the stars that will promote New York City's most ambitious economic development agenda in decades.

Approval or financing was given to a Second Avenue subway; an extension of the Flushing Line to the Far West Side; a spur to connect the Long Island Rail Road to Grand Central Terminal; financing for tens of thousands of apartments for low- and moderate-income residents; the Atlantic Yards complex near Downtown Brooklyn, which includes a new home for the basketball Nets; and even the bus-stop shelters and public toilets that New Yorkers and visitors have demanded for years.
Yes, the subway and LIRR projects would build important infrastructure to boost economic development, but bus shelters (where) and public toilets (where?) do not economic development make.

Nor does the long-delayed arena. The surrounding office space, once promoted as home to 10,000 jobs, had already been severely reduced, and the one planned office tower is on indefinite hold.

And the Times's curious formulation--"financing for tens of thousands of" subsidized apartments--mis-described a revision in the 421-a tax incentive program, which instead led to a rush to get all market-rate buildings started, and produced hundreds of stalled development sites.

Public works?

So I don't blame author Robert Caro for his broad-brush comment to the Times:
In ''The Power Broker,'' Robert A. Caro in 1974 wrote that without the approval of Robert Moses, who oversaw virtually all public works in New York until he was eased out in 1968, the city was ''utterly unable'' to build anything.

Mr. Caro said in an interview that he, too, was struck by the plethora of projects approved in December.

''Does this alignment of stars show that this is may be a problem that democracy can solve?'' he said. ''For the first time in 40 years, I'm hopeful.''
Moses, for all the criticisms he deserved, built public works.

The Atlantic Yards arena, as well as the stadiums mentioned in the article, is a privately-operated building, with profits and naming rights accruing to the private owner, but benefiting from the fig-leaf of public ownership in order to get federal tax-exempt bonds.

Reasons for infrastructure delay

Zupan offered a list of reasons, in no particular order, why it was tougher to build infrastructure today than generations ago:
  • the multiplicity of agencies involved, with different agendas
  • capital programs of limited length, without assured funding for long-term projects
  • competition with funding for a backlog of regular, "state of good repair" maintenance
  • lack of support for long-term projects vs. the instant gratification of ribbon cutting
  • redoing of environmental impact statements when major changes occur
  • changes in administrations, which bring different agendas
  • unexpected cost overruns, sometimes for good reasons, sometimes not
  • a very complex federal environmental review process, NEPA
  • an exacting Federal Transit Administration process
  • opposition by "small but vociferous groups" that larger interests (exemplified by the LIRR's third track project)
  • disagreement in values, such as an emphasis on Manhattan vs. the boroughs
  • an absence of professionalism, replaced by cronyism and political appointees
  • lack of understanding of the economic threat posed by static and crumbling infrastructure
  • the unwillingness to tax ("We expect something for nothing, and it just doesn't happen that way.")
I'll note that a few of those criticisms have been raised in the Atlantic Yards debate; I'd agree that, for truly public projects, such as infrastructure, there should be a way to ensure more rapid progress.

Now we face a significant stall in improvements in the subway and bus system.

An AY footnote

At the end of the program, the panelists were asked about their commutes. Byron said her bicycle commute to Pratt had been "severely compromised" by the closing of the Carlton Avenue Bridge for the Atlantic Yards project--an example of the potential tension between real estate development and transportation.

A bike lane footnote

Asked about issues of walking and biking, Zupan commented, "we have the specter of a former DOT [Department of Transportation] commissioner [Iris Weinshall] suing the city because they're putting a bike lane in Brooklyn--that's horrible."

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.